Search Legislation

The Knottingley Power Plant Order 2015

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

  1. Introductory Text

  2. PART 1

    1. 1.Citation and commencement

    2. 2.Interpretation

  3. PART 2

    1. 3.Development consent etc. granted by the Order

    2. 4.Power to maintain authorised development

  4. PART 3

    1. 5.Operation of generating station

    2. 6.Limits of deviation

    3. 7.Benefit of the Order

    4. 8.Application and modification of legislative provisions

    5. 9.Defence to proceedings in respect of statutory nuisance

  5. PART 4

    1. 10.Street works

    2. 11.Stopping up of street

    3. 12.Public rights of way

    4. 13.Access to works

    5. 14.Agreements with street authorities

  6. PART 5

    1. 15.Discharge of water

    2. 16.Authority to survey and investigate the land

    3. 17.Removal of human remains

  7. PART 6

    1. 18.Compulsory acquisition of land

    2. 19.Compulsory acquisition of land – incorporation of the minerals code

    3. 20.Time limit for exercise of authority to acquire land and rights compulsorily

    4. 21.Compulsory acquisition of rights and imposition of restrictive covenants

    5. 22.Private rights

    6. 23.Application of the Compulsory Purchase (Vesting Declarations) Act 1981

    7. 24.Acquisition of subsoil only

    8. 25.Acquisition of part of certain properties

    9. 26.Rights under or over streets

    10. 27.Temporary use of land for carrying out the authorised development

    11. 28.Temporary use of land for maintaining authorised development

    12. 29.Protective provisions for specified undertakers

    13. 30.Statutory undertakers

    14. 31.Apparatus and rights of statutory undertakers in stopped-up streets

  8. PART 7

    1. 32.Application of landlord and tenant law

    2. 33.Operational land for purposes of the 1990 Act

    3. 34.Felling or lopping of trees and hedgerows

    4. 35.Certification of plans etc.

    5. 36.Arbitration

    6. 37.Procedure in relation to certain approvals etc.

  9. Signature

    1. SCHEDULE 1

      AUTHORISED DEVELOPMENT

      1. PART 1 Authorised Development

      2. PART 2 Requirements

        1. 1.Interpretation

        2. 2.Time limits

        3. 3.Detailed design

        4. 4.Overhead lines and pylons

        5. 5.Cooling water pipelines and pumping station

        6. 6.Gas pipeline and AGI

        7. 7.Provision of landscaping

        8. 8.Implementation and maintenance of landscaping

        9. 9.Footpath/Public Rights of Way diversions

        10. 10.Highway accesses

        11. 11.Temporary buildings, structures and roads

        12. 12.Surface and foul water drainage

        13. 13.Contaminated land and groundwater – general

        14. 14.Contaminated land and groundwater – known contamination on the site of the generating station

        15. 15.Archaeology

        16. 16.Ecological management plan

        17. 17.Construction environment management plan

        18. 18.Common Lane improvement

        19. 19.Air Safety

        20. 20.Flooding – mitigation

        21. 21.Fire prevention

        22. 22.Waste management on site – operational phase

        23. 23.Control of noise – operational phase

        24. 24.European protected species

        25. 25.Restoration of land used temporarily for construction

        26. 26.Air quality monitoring

        27. 27.Combined heat and power

        28. 28.(1) Prior to the operation of Work No, 1, a...

        29. 29. CCS site

        30. 30. CCS monitoring report

        31. 31.Applicability of Requirements 29 and 30

        32. 32.Decommissioning

        33. 33.Requirement for written approval

        34. 34.Approved details

        35. 35.Local liaison committee

        36. 36.Employment and Skills plan

        37. 37.Notice of start and completion of commissioning

        38. 38.Notice of commencement of operation

    2. SCHEDULE 2

      STREETS SUBJECT TO STREET WORKS

    3. SCHEDULE 3

      STREETS TO BE STOPPED UP

      1. STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED

    4. SCHEDULE 4

      PUBLIC RIGHT OF WAY TO BE TEMPORARILY CLOSED AND PERMANENTLY STOPPED UP

      1. PART 1 Claimed public right of way to be extinguished for which a replacement will be provided

      2. PART 2 Rights of way for which a replacement will be provided during temporary closure

      3. PART 3 Rights of way for which no replacement will be provided during temporary closure

    5. SCHEDULE 5

      ACCESS TO WORKS

    6. SCHEDULE 6

      MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF RESTRICTIVE COVENANTS

      1. 1.Compensation enactments

      2. 2.(1) Without prejudice to the generality of paragraph 1, the...

      3. 3.Application of the 1965 Act

      4. 4.For section 7 of the 1965 Act (measure of compensation)...

      5. 5.For section 8 of the 1965 Act (provisions as to...

      6. 6.The following provisions of the 1965 Act (which state the...

      7. 7.Section 11 of the 1965 Act (powers of entry) is...

      8. 8.Section 20 of the 1965 Act (tenants at will, etc.)...

      9. 9.Section 22 of the 1965 Act (interests omitted from purchase)...

      10. 10.In this Schedule, “acquiring authority” has the same meaning as...

    7. SCHEDULE 7

      PROCEDURE FOR DISCHARGE OF REQUIREMENTS

      1. 1.Applications made under requirement

      2. 2.Further information

      3. 3.Fees

      4. 4.Appeals

      5. 5.Interpretation of Schedule 7

    8. SCHEDULE 8

      PROTECTIVE PROVISIONS

      1. For the protection of Canal and River Trust

        1. 1.Interpretation

        2. 2.Powers requiring CRT’s consent

        3. 3.Vehicles, plant and machinery

        4. 4.Fencing

        5. 5.Survey of waterway

        6. 6.Approval of plans, protective works etc.

        7. 7.Design of works

        8. 8.Notice of works

        9. 9.Lighting

        10. 10.Construction of specified works

        11. 11.Prevention of pollution

        12. 12.Access to work – provision of information

        13. 13.Alterations to the waterway

        14. 14.Maintenance of works

        15. 15.Repayment of CRT’s fees, etc.

        16. 16.Costs of alterations, etc.

        17. 17.Making good of detriment; compensation and indemnity, etc.

        18. 18.Arbitration

        19. 19.Capitalised sums

  10. Explanatory Note

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources