Search Legislation

The River Humber Gas Pipeline Replacement Order 2016

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Section 3

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the The River Humber Gas Pipeline Replacement Order 2016, Section 3. Help about Changes to Legislation

Application, modification and disapplication of legislative provisionsE+W+S

3.—(1) The following provisions do not apply in relation to the construction of works carried out for the purpose of, or in connection with, the construction or maintenance of the authorised project—

(a)[F1the Environmental Permitting (England and Wales) Regulations 2016], to the extent that they require a permit for anything that would have required consent under section 109 of the Water Resources Act 1991 immediately before the repeal of that section;

(b)The provisions of any byelaws made under paragraphs 5, 6 or 6a of Schedule 25 to the Water Resources Act 1991, which require consent or approval for the carrying out of the works.

(2) A power conferred by this Order may be exercised despite, and without having regard to, any provision of byelaws made by the East Riding of Yorkshire Council in its capacity as lead local flood authority but this paragraph does not apply to a provision which permits the taking of any action with the consent of East Riding of Yorkshire Council, of an internal drainage board or of the Environment Agency.

Textual Amendments

Commencement Information

I1Art. 3 in force at 15.9.2016, see art. 1

Back to top

Options/Help