25.—(1) The Petroleum Licensing (Applications) Regulations 2015(1) are amended as follows.
(2) In regulation 2 (interpretation)—
(a)in the definition of “application notice”, for “Secretary of State” substitute “OGA”;
(b)in the definition of “block”, for “Department of Energy and Climate Change” substitute “OGA”;
(c)after the definition of “model clauses” insert—
““the OGA” means the Oil and Gas Authority;”.
(3) In regulation 4 (applications for licences: general)—
(a)in paragraph (2)(a), omit “by the Department of Energy and Climate Change”;
(b)in paragraph 2(d), for “regulation 7” substitute “the Oil and Gas Authority (Fees) Regulations 2016(2)”.
(c)in paragraph (6), for “Secretary of State” (in both places) substitute “OGA”;
(d)in paragraph (8), for “Secretary of State” substitute “OGA”.
(4) In regulation 5(6) (applications for a petroleum exploration and development licence or a seaward area production licence), for “Secretary of State” (in both places) substitute “OGA”.
(5) Omit regulation 7 (fees).
(6) In regulation 8 (form of licences), for “Secretary of State” substitute “OGA”.
(7) After regulation 8, insert—
9.—(1) The Secretary of State must from time to time—
(a)carry out a review of these Regulations;
(b)set out the conclusions of the review in a report; and
(c)publish the report.
(2) The report must in particular—
(a)set out the objectives intended to be achieved by these Regulations;
(b)assess the extent to which those objectives are achieved;
(c)assess whether those objectives remain appropriate and, if so, the extent to which they could be achieved in a less burdensome way.
(3) The first report under this regulation must be published before the end of the period of five years beginning with the day on which this regulation comes into force.
(4) Subsequent reports under this regulation must be published at intervals not exceeding five years.”.
(8) In paragraph 6 of Schedule 2 (information and supporting documentation required for an application for a petroleum exploration and development licence or a seaward area production licence), for “Secretary of State” substitute “OGA”.
(9) In paragraph 2 of Schedule 3 (additional information and supporting documentation required for an application for a seaward area production licence), for “Secretary of State” substitute “OGA”.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: