- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
18.—(1) Part 1 of the 1965 Act, in so far as not modified by or inconsistent with the provisions of this Order, applies to the acquisition of land under this Order—
(a)as it applies to a compulsory purchase to which the 1981 Act applies; and
(b)as if this Order were a compulsory purchase order under that Act.
(2) Part 1 of the 1965 Act, as applied by paragraph (1), has effect with the following modifications.
(3) Omit section 4 (which provides a time limit for compulsory purchase of land).
(4) In section 4A(1)(1) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to the High Court in respect of compulsory purchase order), the three year period mentioned in section 4”, substitute “section 22 of the Transport and Works Act 1992 (validity of orders under section 1 or 3), the five year period mentioned in article 29 (time limit for exercise of powers of acquisition) of the Network Rail (Hope Valley Capacity) Order 2018(2)”.
(5) In section 11(1B)(3) (powers of entry) in a case where the notice to treat relates only to the acquisition of an easement or other right over land, for “3 months” substitute “1 month”.
(6) In section 11A(4) (powers of entry: further notices of entry)—
(a)in subsection (1)(a), after “land” insert “under that provision”;
(b)in subsection (2), after “land” insert “under that provision”.
(7) In section 22(2) (expiry of time limit for exercise of compulsory purchase power not to affect acquisition of interests omitted from purchase), for “section 4 of this Act” substitute “article 29 (time limit for exercise of powers of acquisition) of the Network Rail (Hope Valley Capacity) Order 2018(5)”.
(8) In Schedule 2A(6) (counter-notice requiring purchase of land not in notice to treat)—
(a)for paragraphs 1(2) and 14(2) substitute—
“(2) But see articles 21(4) (cases where powers of acquisition limited to ground anchor rights) and 22(3) (power to acquire subsoil or airspace only) of the Network Rail (Hope Valley Capacity) Order 2018, which exclude acquisition with respect to ground anchor rights only and the acquisition of subsoil or airspace only from this Schedule.”; and
(b)after paragraph 29, insert—
30. In this Schedule, references to entering on and taking possession of land do not include doing so under article 15 (protective works to buildings), 24 (temporary use of land for construction of works) or 25 (temporary use of land for maintenance of works) of the Network Rail (Hope Valley Capacity) Order 2018.”
As inserted by section 202(1) of the Housing and Planning Act 2016 (c. 22).
Subsection (1B) of section 11 was inserted by section 186(1) and (2)(b) of the Housing and Planning Act 2016 (c. 22).
As inserted by section 186(3) of the Housing and Planning Act 2016 (c. 22).
As inserted by paragraph 3 of Schedule 3 to the Housing and Planning Act 2016 (c. 22).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: