Regulation 28
Regulation 15(2)
The contractual agreement referred to in regulation 15(2) must specify provisions of regulation 15(2) to (8) and include at least the following elements—
(a)the scope of the agreement as regards infrastructure and service facilities, structured in accordance with Schedule 1 (services to be supplied to railways undertakings). It must cover all aspects of infrastructure management, including maintenance and renewal of the infrastructure already in operation. Where appropriate, construction of new infrastructure may also be covered;
(b)the structure of payments or funds allocated to the infrastructure services listed in Schedule 1, to maintenance and renewal and to dealing with existing maintenance and renewal backlogs. Where appropriate, the structure of payments or funds allocated to new infrastructure may be covered;
(c)user-oriented performance targets, in the form of indicators and quality criteria covering elements such as—
(i)train performance, such as in terms of line speed and reliability, and customer satisfaction,
(ii)network capacity,
(iii)asset management,
(iv)activity volumes,
(v)safety levels, and
(vi)environmental protection;
(d)the amount of possible maintenance backlog and the assets which will be phased out of use and therefore trigger different financial flows;
(e)the incentives referred to in regulation 15(3);
(f)minimum reporting obligations for the infrastructure manager in terms of content and frequency of reporting, including information to be published annually;
(g)the agreed duration of the agreement, which must be synchronised and consistent with the duration of the infrastructure manager’s business plan, concession or licence, where appropriate, and the charging framework and rules set by the Department under regulation 14(1);
(h)rules for dealing with major disruptions of operations and emergency situations, including contingency plans and early termination of the contractual agreement, and timely information to users;
(i)remedial measures to be taken if either of the parties is in breach of its contractual obligations, or in exceptional circumstances affecting the availability of public funding; this includes conditions and procedures for renegotiation and early termination.”
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: