Conditions on exemptions

This section has no associated Explanatory Memorandum

4.  The exemption granted by article 3(a) of this Order is subject to compliance with the following conditions—

(a)Lostock Sustainable Energy Plant is connected to the total system;

(b)Lostock Sustainable Energy Plant does not export more than 100 megawatts of electrical power to the total system, except in circumstances outside the reasonable control of Lostock Sustainable Energy Plant Limited; and

(c)Lostock Sustainable Energy Plant Limited is not a licensed generator.