Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
53.—(1) The Authority may serve a notice (an “enforcement notice”) on a scheme supplier where—
(a)the Authority is satisfied that the scheme supplier has failed to pay—
(i)a quarterly levy payment in accordance with regulation 40,
(ii)a levy credit payment in accordance with regulation 42,
(iii)any additional credit cover,
(iv)a backdated levy payment in accordance with regulation 49,
(v)a mutualisation payment in accordance with regulation 56, or
(vi)interest on a payment referred to in paragraph (i), (iv) or (v) due in accordance with regulation 54, or
(b)the Authority reasonably believes that the scheme supplier has failed to comply with any other obligation imposed on scheme suppliers under Part 7, 8, or 9.
(2) An enforcement notice served in the circumstances referred to in paragraph (1)(a) must—
(a)specify—
(i)the amount of quarterly levy payment, levy credit payment, additional credit cover, backdated levy payment, or mutualisation payment the scheme supplier has failed to pay (the “outstanding amount”),
(ii)where applicable, how the outstanding amount has been calculated,
(iii)where regulation 54 (interest on late payments) applies, any interest due on the outstanding amount at the date the enforcement notice is served and how that amount of interest has been calculated,
(iv)the sum of the outstanding amount and the interest due (“the total amount due”),
(v)the date by which the scheme supplier must pay the total amount due or, where the outstanding amount is a levy credit payment or additional credit cover, the date by which they must pay the total amount due or provide an acceptable letter of credit (or both) in respect of that amount, and
(vi)how the total amount due must be paid, and
(b)include information about the matters mentioned in—
(i)regulation 55 (draw down of credit cover), and
(ii)regulation 56 (mutualisation).
(3) An enforcement notice served in the circumstances referred to in paragraph (1)(b) must specify—
(a)the provision of these Regulations which the Authority believes has been breached,
(b)the matters constituting the breach,
(c)the steps the scheme supplier must take to remedy the breach, and
(d)the date by which those steps must be taken.
(4) An enforcement notice must include information about appeals under regulation 60.
(5) The Authority must publish an enforcement notice, and any other notice served under paragraph (6), as soon as reasonably practicable after the date on which it is served.
(6) An enforcement notice may be varied or revoked at any time by the Authority by serving a further notice, including a further enforcement notice, on the scheme supplier.
(7) A scheme supplier on whom an enforcement notice is served must comply with the requirements of that enforcement notice.
(8) The duty imposed by paragraph (7) is enforceable in civil proceedings by the Authority for—
(a)an injunction,
(b)specific performance of a statutory duty under section 45 of the Court of Session Act 1988(1), or
(c)any other appropriate relief.
Commencement Information
I1Reg. 53 in force at 30.11.2021, see reg. 1(1)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: