23.—(1) Network Rail may acquire compulsorily so much of, or such rights in, the subsoil of or the airspace over the land referred to in paragraph (1)(a) or (b) of article 19 (power to acquire land) as may be required for any purpose for which that land may be acquired under that provision instead of acquiring the whole of the land.
(2) Where Network Rail acquires any part of, or rights in, the subsoil of or the airspace over land under paragraph (1), Network Rail is not required to acquire an interest in any other part of the land.
(3) Paragraph (2) does not prevent Schedule 2A to the 1965 Act (as modified by article 20 (application of Part 1 of the 1965 Act)) or Schedule A1 to the 1981 Act (as modified by article 21 (application of the 1981 Act)) from applying where Network Rail acquires a cellar, vault, arch or other construction forming part of a house, building or manufactory.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: