Compulsory acquisition of land – incorporation of the mineral codeE+W+S

24.  Parts 2 and 3 of Schedule 2 (minerals) to the Acquisition of Land Act 1981(1) are incorporated into this Order subject to the modifications that—

(a)paragraph 8(3) is not incorporated;

(b)for “the acquiring authority” substitute “the undertaker”; and

(c)for “undertaking” substitute “authorised development”.

Commencement Information

I1Art. 24 in force at 2.9.2022, see art. 1