There are currently no known outstanding effects for the The Awel y Môr Offshore Wind Farm Order 2023.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
PART 6 Miscellaneous and general
2.(1) Without limitation on the scope of paragraph 1, the...
3.(1) Without limitation on the scope of paragraph 1, the...
6.For section 7 (measure of compensation in case of severance)...
7.The following provisions of the 1965 Act (which state the...
10.Section 22 (interests omitted from purchase) of the 1965 Act...
11.For Schedule 2A of the 1965 Act substitute— SCHEDULE 2A...
PART 1 Protection for electricity, gas, water and sewerage undertakers
PART 3 For the protection of National Grid
24.(1) Before beginning to construct any National Grid connection works,...
25.(1) Any approval of National Grid required under this Schedule—...
26.(1) The undertaker must give to National Grid not less...
28.Apparatus of National Grid in streets subject to temporary stopping up
33.Retained apparatus: Protection of National Grid as Electricity Undertaker
PART 4 For the protection of SP Manweb as electricity undertaker
PART 5 Protection for operators of electronic communications code networks
PART 6 For the protection of Network Rail Infrastructure Limited
58.The provisions of this Part have effect unless otherwise agreed...
59.In this Part— “asset protection agreement” means an agreement to...
61.(1) The undertaker must not exercise the powers conferred by—...
62.(1) The undertaker must before commencing construction of any specified...
64.The undertaker must— (a) at all times afford reasonable facilities...
65.Network Rail must at all times afford reasonable facilities to...
66.(1) If any permanent or temporary alterations or additions to...
67.The undertaker must repay to Network Rail all reasonable fees,...
68.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
70.The undertaker must not provide any illumination or illuminated sign...
71.Any additional expenses that Network Rail may reasonably incur in...
75.The undertaker and Network Rail may, subject in the case...
76.Nothing in this Order, or in any enactment incorporated with...
77.The undertaker must give written notice to Network Rail where...
PART 8 For the protection of Conwy County Borough Council
90.The provisions of this Part have effect unless otherwise agreed...
91.In this Part— “OPNMP” means Offshore Piling Noise Monitoring Plan,...
92.(1) Prior to the commencement of any offshore piling as...
93.(1) The undertaker may, at any time following approval of...
94.The authorised development must be carried out in accordance with...
95.The undertaker will give Conwy County Borough Council not less...
96.Nothing in any OPNMP may conflict with requirement 4 of...
97.Any approval required under this Part must not be unreasonably...
98.Any difference or dispute arising between the undertaker and Conwy...
PART 10 For the protection of Welsh Ministers as Strategic Highway Authority
113.(1) Prior to the commencement of the works the undertaker...
114.No crossing is to take place until a monitoring regime...
117.The undertaker must contact any owners or operators of apparatus...
120.The undertaker (or any person carrying out works on its...
122.The undertaker must execute the works in strict accordance with...
124.Exercise of the right to inspect under paragraph 123 must...
125.If required by the WM, the undertaker must provide link...
126.(1) The undertaker must compensate the WM in respect of...
129.Any and all costs associated with the reinstatement work will...
131.The undertaker must supply the WM with as built records...
132.The undertaker must submit a Geotechnical Feedback Report (GFR as...
133.After the apparatus has been placed, the undertaker must not...
137.If the apparatus is abandoned or the consent is surrendered...
138.If the undertaker proposes to part with his interest in...
PART 11 For the protection of North Hoyle Wind Farm Limited
142.Requirement for approval of method statement and surveys
145.In granting its approval (or deemed approval) of the method...
146.The undertaker must use all reasonable endeavours to ensure the...
149.The undertaker must ensure that the specified work are carried...
150.Any contractor and/or subcontractor used by the undertaker for the...
151.Either during the installation or as soon as practicable after...
152.The undertaker must provide the Company with the actual as-laid...
153.The undertaker must ensure that the risk of dropped object,...
155.Notwithstanding the provisions of paragraph 154, if any future specified...
156.Subject to paragraphs 154 and 155, where the undertaker requires...
160.The undertaker is responsible for the recovery or removal and...
162.In the event of the undertaker being liable for damage...
163.The undertaker must use reasonable endeavours to procure that any...
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: