This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
3. In Schedule 1 to the 2022 Order (Authorised Development), in the description of Work no. 1 in 1B replace “with a net rated electrical output of up to 150 MW for four hours consisting of” with “having a combination of net rated electrical output and duration that delivers an electrical capacity of up to 600MWh, which may comprise—
(i)a net rated electrical output of 150MW for up to 4 hours
(ii)a net rated electrical output of 240MW for up to 2 hours and 30 minutes;
(iii)a net rated electrical output of 300MW for up to 2 hours;
(iv)a net rated electrical output of 400MW for up to 1 hour and 30 minutes; or
(v)a net rated electrical output of 600MW for up to 1 hour; and which consists of;
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: