Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
2.—(1) This paragraph applies where, in relation to work to a particular building, full plans were deposited with a local authority before 1st October 2023 and in accordance with any provision of Part 1 of the 1984 Act or a local enactment the local authority has rejected those plans on or after that date (“the rejection date”).
(2) Where this paragraph applies then with effect from the rejection date the regulator, and not the local authority for the area, is the building control authority in relation to the higher-risk building and accordingly—
(a)the duties and functions of the regulator under section 91 of the 1984 Act apply in relation to the higher-risk building or any proposed higher-risk building;
(b)Parts 2 to 6 of these Regulations apply to any HRB work or work to existing HRB from the rejection date with the modifications provided in this paragraph except that regulation 47 (regularisation) does not apply in relation to any work carried out before the rejection date and accordingly any reference to a regularisation certificate in Parts 2 to 6 of these Regulations is to be ignored, and
(c)the 2010 Regulations, to the extent they apply to higher-risk buildings, apply to any of the work from the rejection date.
(3) Within 10 working days of the rejection date the person intending to carry out the work must give a notice to the regulator setting out—
(a)the name, address, telephone number and (if available) email address of the person intending to carry out the work;
(b)details of the work to be carried out;
(c)details of any existing building on the site, including the height of any existing building, the number of storeys contained in it and the use of each storey (regulations 5 and 6 of the Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023(1) have effect in determining the height and the number of storeys in a building);
(d)details of the intended use of the higher-risk building, including the intended use of each storey;
(e)the height of the higher-risk building as determined in accordance with regulation 5 of the Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023;
(f)the number of storeys in the higher-risk building as determined in accordance with regulation 6 of the Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023;
(g)where the work is HRB work or is work to existing HRB which changes the number of residential or commercial units in the building, the proposed number of flats, number of residential rooms and number of commercial units to be contained in the higher-risk building;
(h)details of the work which has been carried out together with a summary of the inspections undertaken by the local authority in relation to the work.
(4) Where any work was carried out before the rejection date the person who carried out the work or the owner must comply with any notice from the regulator requiring them within a reasonable time to cut into, lay open or pull down so much of the work as prevents the regulator from ascertaining whether the work contravenes any requirement of the building regulations.
(5) Where any work was carried out before the rejection date (“the HRB project”) and on or after that date a building control approval application for HRB work or a building control approval application for work to existing HRB is submitted to the regulator in respect of the HRB project, then in addition to the requirements of regulation 4 the person who carried out the work must provide the regulator with such plans as are necessary to show the work already carried out complies with all applicable requirements of the building regulations.
Commencement Information
I1Sch. 3 para. 2 in force at 1.10.2023, see reg. 1(1)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: