Amendment of regulation 28 (contract completion report)

This section has no associated Explanatory Memorandum

33.  In regulation 28(1)—

(a)in paragraph (2)—

(i)in the opening words, for the “The report” substitute “Subject to paragraphs (3) to (7), the report”;

(ii)after sub-paragraph (b) insert—

(ba)where the contract contains components, an explanation of which of those deliverables relate to which component;;

(iii)in sub-paragraph (c)(i), at the end insert “and, where the contract contains components, an explanation of which parts of any risk contingency element relate to which component”;

(iv)in sub-paragraph (c)(ii), after “element” insert “and, where the contract contains components, an explanation of which parts of any actual risk contingency element relate to which component”;

(v)in sub-paragraph (c)(iii)—

(aa)after “profit” insert “for the contract and, where the contract contains components, for each component”;

(bb)for “5” substitute “3”;

(vi)in sub-paragraph (c)(iv), at the end insert “for the contract and, where the contract contains components, for each component”;

(vii)in sub-paragraph (c)(v), after “profit” insert “for the contract and, where the contract contains components, for each component”;

(viii)in sub-paragraph (c)(vi), after “profit” insert “for the contract and, where the contract contains components, for each component”;

(ix)for sub-paragraph (d) substitute—

(d)an annual profile of any estimated costs for the contract and, where the contract contains components, for each component at the time of agreement (split by the defined pricing structure);;

(x)for sub-paragraph (e) substitute—

(e)the total amount of non-recurring allowable costs (split by the defined pricing structure) for the contract and, where the contract contains components, for each component of the contract, except where the contract or component was priced using a contract pricing method under which costs are indistinguishable from profits;;

(xi)in sub-paragraph (g), at the end insert “for the contract and, where the contract contains components, each component of the contract”;

(xii)in sub-paragraph (i), after “price” insert “of the contract and, where the contract contains components, each component of the contract”;

(xiii)in sub-paragraph (j)—

(aa)in the opening words, after “contract”, in the second place it occurs, insert “or, where the contract contains components, a component of the contract”;

(bb)in paragraph (ii), after “price” insert “for the contract or component”;

(cc)in paragraph (iii), at the end insert “or component”;

(xiv)after sub-paragraph (o) insert—

(oa)where the contract contains components, an explanation of which delivery milestones relate to which component;;

(xv)omit the “and” at the end of sub-paragraph (p)(ix);

(xvi)in sub-paragraph (q)(iii), for “sub-contract.” substitute “sub-contract; and”;

(xvii)after sub-paragraph (q) insert—

(r)a description of any component completion reports provided under regulation 27A.;

(b)after paragraph (2) insert—

(3) If the contract price for the contract or component is determined entirely in accordance with regulation 19A (commercial pricing) or regulation 19B(3) (prices determined in accordance with law) the requirements in paragraphs (2) are modified as follows in relation to the contract or component—

(a)the actual quantum of deliverables required by paragraph (2)(b) need not be expressed using the output metrics set out in the contract reporting plan;

(b)the report need not contain the information specified in paragraphs (2)(c)(i), (ii), (v) and (vi), (b) to (h), (k), (p) and (q);

(c)paragraph (2)(i) has effect as if for the words from “any estimated” to the end there were substituted “the contract price of the contract or component estimated at the time of agreement and the actual contract price of the contract or component”;

(d)paragraph (2)(j)(iii) has effect as if for “costs already incurred or forecast to be incurred under the contract or component” there were substituted “price payable, together with a quantified analysis of the variance”.

(4) If the contract price for the contract or component is determined entirely in accordance with regulation 19C (previously agreed price) the requirements in paragraphs (2) are modified as follows in relation to the contract or component—

(a)paragraph (2)(a) has effect as if at the end there were inserted “which were deliverable after the contract has become a qualifying defence contract”;

(b)paragraph (2)(b) has effect as if after “expressed” there were inserted “in respect of those deliverables that were deliverable after the contract became a qualifying defence contract”;

(c)the report need not contain the information specified in paragraph (2)(c), (e) and (p);

(d)paragraph (2)(i) has effect as if for the words from “any estimated” to the end there were substituted “the contract price for the contract or component estimated at the time of agreement and the actual contract price for the contract or component”;

(e)paragraph (2)(j) has effect as if for “was entered into” there were substituted “became a qualifying defence contract”;

(f)paragraph (2)(m) has effect as if at the end there were inserted “after the contract became a qualifying defence contract”;

(g)paragraph (2)(n) has effect as if at the end there were inserted “after the contract became a qualifying defence contract”;

(h)paragraph (2)(o) has effect as if—

(i)in paragraph (2)(o)(i) at the end there were inserted “after the contract became a qualifying defence contract”;

(ii)paragraph (2)(o)(ii) were omitted.

(5) If the contract price for the contract or component is determined entirely in accordance with regulation 19E (competed rates applied to uncompeted volumes) in relation to the contract or component—

(a)paragraph (2)(f) has effect as if for “cost recovery base” there were substituted “competed rates”;

(b)paragraph (2)(h) has effect as if for “cost recovery base” there were substituted “competed rates”.

(6) The report need not separately identify any information in relation to a component which has been provided in a report under regulation 27A (component completion report)..

(1)

Regulation 28 was amended by S.I. 2019/1106.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources