Print Options
PrintThe Whole
Instrument
PrintThe Whole
Part
PrintThis
Section
only
Changes over time for: Section 33


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
This version of this provision is prospective.

Status
The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section. A version of a provision is prospective either:
- where the provision (Part, Chapter or section) has never come into force or;
- where the text of the provision is subject to change, but no date has yet been appointed by the appropriate person or body for those changes to come into force.
Commencement Orders listed in the ‘Changes to Legislation’ box as not yet applied may bring this prospective version into force.
Changes to legislation:
There are outstanding changes not yet made by the legislation.gov.uk editorial team to The M3 Junction 9 Development Consent Order 2024. Any changes that have already been made by the team appear in the content and are referenced with annotations.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Changes and effects yet to be applied to Article 33:
Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
Prospective
Rights under or over streetsE+W
33.—(1) The undertaker may enter on and appropriate so much of the subsoil of, or airspace over, any street within the Order limits as may be required for the purposes of the authorised development and may use the subsoil or airspace for those purposes or any other purpose ancillary to the authorised development.
(2) Subject to paragraph (3), the undertaker may exercise any power conferred by paragraph (1) in relation to a street without being required to acquire any part of the street or any easement or right in the street.
(3) Paragraph (2) does not apply in relation to—
(a)any subway or underground building; or
(b)any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.
(4) Subject to paragraph (5), any person who is an owner or occupier of land in respect of which the power of appropriation conferred by paragraph (1) is exercised without the undertaker acquiring any part of that person’s interest in the land, and who suffers loss as a result, is entitled to compensation to be determined as if it were a dispute under Part 1 of the 1961 Act.
(5) Compensation is not payable under paragraph (4) to any person who is a statutory undertaker to whom section 85 (sharing of cost of necessary measures) of the 1991 Act applies in respect of measures of which the allowable costs are to be borne in accordance with that section.