118.—(1) The undertaker may not exercise the powers conferred by—
(a)article 3 (development consent etc granted by the Order);
(b)article 5 (power to maintain the authorised development);
(c)article 16 (discharge of water);
(d)article 19 (authority to survey and investigate the land);
(e)article 20 (compulsory acquisition of land);
(f)article 22 (compulsory acquisition of rights);
(g)article 23 (private rights);
(h)article 25 (acquisition of subsoil only);
(i)article 26 (power to override easements and other rights);
(j)article 29 (temporary use of land for constructing the authorised development);
(k)article 30 (temporary use of land for maintaining the authorised development);
(l)article 31 statutory undertakers);
(m)article 38 (felling or lopping of trees and removal of hedgerows);
(n)article 39 (trees subject to tree preservation orders);
(o)the powers conferred by section 11(3) (power of entry) of the 1965 Act;
(p)the powers conferred by section 203 (power to override easements and rights) of the Housing and Planning Act 2016;
(q)the powers conferred by section 172 (right to enter and survey land) of the Housing and Planning Act 2016;
in respect of any railway property unless the exercise of such powers is with the consent of Network Rail.
(2) The undertaker may not in the exercise of the powers conferred by this Order prevent pedestrian or vehicular access to any railway property, unless preventing such access is with the consent of Network Rail.
(3) The undertaker may not exercise the powers conferred by sections 271 or 272 of the 1990 Act, article 31 (statutory undertakers), article 26 (power to override easements and other rights) or article 23 (private rights), in relation to any right of access of Network Rail to railway property, but such right of access may be diverted with the consent of Network Rail.
(4) The undertaker may not under the powers of this Order acquire or use or acquire new rights over, or seek to impose any restrictive covenants over, any railway property, or extinguish any existing rights of Network Rail in respect of any third party property, except with the consent of Network Rail.
(5) The undertaker may not under the powers of this Order do anything which would result in railway property being incapable of being used or maintained or which would affect the safe running of trains on the railway.
(6) Where Network Rail is asked to give its consent pursuant to this paragraph, such consent may not be unreasonably withheld but may be given subject to reasonable conditions but it may not be unreasonable to withhold consent for reasons of operational or railway safety (such matters to be in Network Rail’s absolute discretion).
(7) The undertaker must enter into an asset protection agreement prior to the carrying out of any specified work.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: