4.—(1) This regulation applies where an approved inspector has not become a suitably qualified registered building control approver before 6 April 2024.
(2) Where an approved inspector is overseeing higher-risk building work before 6 April 2024, then—
(a)an approved inspector must not continue to oversee higher-risk building work on or after 6 April 2024;
(b)any initial notice submitted by the approved inspector in respect of higher-risk building work is cancelled;
(c)responsibility for overseeing higher-risk building work will transfer to the local authority.
(3) Where an approved inspector is overseeing building work that is not higher-risk building work, then—
(a)until but not including 1 October 2024, an approved inspector may continue to oversee building work;
(b)any initial notices submitted by the approved inspector will cease to be in force on 1 October 2024;
(c)any building work that is not completed before 1 October 2024 will transfer to the local authority unless a registered building control approver, who is not the same person as the approved inspector, has submitted a new initial notice for that work and the notice is accepted or is deemed to be accepted;
(d)until but not including 1 October 2024, an approved inspector may continue to issue a plans certificate(1), a final certificate(2), and an amendment notice(3) in respect of building work.
(4) Where an amendment notice is issued before 1 October 2024 and that notice changes the nature of the building work specified in the initial notice so that it becomes higher-risk building work, such work must be transferred to the local authority.
See the definition of “plans certificate” in section 50 of the Building Act 1984.
See the definition of “final certificate” in section 51 of the Building Act 1984.
See the definition of “amendment notice” in section 51A of the Building Act 1984.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: