Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 61


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 01/04/2015.
Changes to legislation:
There are currently no known outstanding effects for the Planning Act (Northern Ireland) 2011, Section 61.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Duration of planning permissionN.I.
This section has no associated Explanatory Notes
61—(1) Subject to this section, every planning permission granted or deemed to be granted shall be granted or, as the case may be, deemed to be granted subject to the condition that the development to which it relates must be begun within—
(a)5 years of the date on which the permission is granted; or
(b)such other period (whether longer or shorter) as the authority concerned with the terms of the planning permission considers appropriate having regard to the provisions of the local development plan and to any other material considerations.
(2) If planning permission is granted without the condition required by subsection (1), it shall be deemed to have been granted subject to the condition that the development to which it relates must be begun within 5 years of the date of the grant.
(3) Nothing in subsections (1) and (2) applies—
(a)to any outline planning permission;
(b)to any planning permission granted by a development order;
(c)to any planning permission granted for a limited period;
(d)to any planning permission granted for development carried out before the grant of that permission;
(e)to any planning permission granted by an enterprise zone scheme; or
(f)to any planning permission granted by a simplified planning zone scheme.