SCHEDULES
F3SCHEDULE 8BNEW BUILDINGS (COMPLETION DAYS)
Completion notices
1
1
If it appears to the Department that the work remaining to be done on a new building is such that the building can reasonably be expected to be completed within three months, the Department may serve a completion notice on the person entitled to possession of the building.
2
If it appears to the Department that a new building has been completed the Department may serve a completion notice on the person entitled to possession of the building.
3
The Department may withdraw a completion notice by serving on the person entitled to possession of the building a subsequent completion notice.
4
Where an appeal under paragraph 4 has been brought against a completion notice, the power conferred by sub-paragraph (3) shall only be exercisable with the consent in writing of the person entitled to possession of the building to which the notice relates.
5
The power conferred by sub-paragraph (3) shall cease to be exercisable in relation to a completion notice once a day has been determined under this Schedule as the completion day in relation to the building to which the notice relates.
6
F1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
7
F1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8
F1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F29
The Department shall not serve a completion notice in relation to a building of a prescribed class.
2004 NI 4