PART IIN.I.ELECTRICITY SUPPLY

Licensing of supply, etc.N.I.

[F1CertificationN.I.

10E.(1) The Authority must, within the 4 months beginning with the day on which it receives an application for certification, make a preliminary decision as to whether it should certify the applicant.

(2) If—

(a)the Authority has asked an applicant or a relevant producer or supplier or related transmission licensee for information under Article 10C(7) or (8); and

(b)the information has not been supplied by the date specified by the Authority under Article 10C(9),

then the period of 4 months referred to in paragraph (1) shall be extended by the period of delay in supplying such information.

(3) As soon as is reasonably practicable after making the preliminary decision under paragraph (1), the Authority must notify the decision and the reasons for it to—

(a)the applicant;

(b)any related transmission licensee;

(c)the Department; and

(d)the European Commission.

(4) The Authority must enclose with the notification under paragraph (3)(a), (b) or (d) a copy of any report which the Department has prepared under Article 10D in respect of the applicant and which the Authority receives before giving the notification.

(5) [F2Article 51] of the Electricity Regulation sets out the obligation to make a final decision, together with related processes, time limits, matters to be taken into account and conditions.

(6) As soon as is reasonably practicable after making the final decision in any case, the Authority must notify the decision and the reasons for it to—

(a)the applicant;

(b)any related transmission licensee;

(c)the Department; and

(d)the European Commission.]