xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

SCHEDULE 4N.I.OTHER POWERS, ETC., OF LICENCE HOLDERS

Temporary continuation of wayleavesN.I.

12.—(1) This paragraph applies where at any time such a wayleave as is mentioned in paragraph 10 (whether granted under that paragraph or by agreement between the parties)—N.I.

(a)is determined by the expiration of a period specified in the wayleave;

(b)is terminated by the owner or occupier of the land in accordance with a term contained in the wayleave; or

(c)by reason of a change in the ownership or occupation of the land after the granting of the wayleave, ceases to be binding on the owner or occupier of the land.

(2) The owner or occupier of the land may—

(a)in a case falling within sub-paragraph (1)(a), at any time after or within 3 months before the end of the period specified in the wayleave;

(b)in a case falling within sub-paragraph (1)(b), at any time after the wayleave has been terminated by him; or

(c)in a case falling within sub-paragraph (1)(c), at any time after becoming the owner or occupier of the land by virtue of such a change in the ownership or occupation of the land as is mentioned in that sub-paragraph,

give to the licence holder a notice requiring him to remove the electric line from the land; but the licence holder shall not be obliged to comply with such a notice except in the circumstances and to the extent provided by the following provisions of this paragraph.

(3) Where within the period of 3 months from the date of the notice under sub-paragraph (2) the licence holder makes neither—

(a)an application for the grant of the necessary wayleave under paragraph 10; nor

(b)an application for a vesting order under paragraph 1 of Schedule 3 in respect of the land,

the licence holder shall comply with the notice at the end of that period.

(4) Where—

(a)within the period mentioned in sub-paragraph (3) the licence holder makes an application for the grant of the necessary wayleave under paragraph 10; and

(b)that application is refused by the Department,

the licence holder shall comply with the notice under sub-paragraph (2) at the end of the period of one month from the date of the Department's decision or such longer period as the Department may specify.

(5) Where—

(a)within the period mentioned in sub-paragraph (3) the licence holder makes an application for a vesting order under paragraph 1 of Schedule 3 in respect of the land; and

(b)that order is not made by the Department,

the licence holder shall comply with the notice under sub-paragraph (2) at the end of the period of one month from the date of the Department's decision or such longer period as the Department may specify.