PART IIGAS SUPPLY AND ASSOCIATED ACTIVITIES
Major pipe-lines, gas storage facilities and gas processing facilities
F1Increase of capacity of LNG facility38B
1
If in the case of an LNG facility operated by a person holding a licence under Article 8(1)(d) (“the operator”) it appears to the Authority, on the application of a person other than the operator, that the LNG facility can be modified to increase the capacity of that facility, then, subject to paragraph (2), the Authority may, after giving to the operator an opportunity of being heard about the matter, give directions to the operator in consequence of the application.
2
Paragraphs (2) to (7) of Article 36 apply in relation to directions under paragraph (1) of this Article as they apply in relation to directions under paragraph (1) of that Article.