Changes over time for: Section 7B

 Help about opening options

Alternative versions:

Status:

Point in time view as at 25/07/2014.

Changes to legislation:

The Gas (Northern Ireland) Order 1996, Section 7B is up to date with all changes known to be in force on or before 02 July 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

[F17B.(1) Any condition specified in an order under Article 7(1)(c) in respect of a conveyance exemption which requires the approval of the Authority for the methodology of calculating a system charge in relation to a distribution system or which imposes any obligation on the holder of the exemption in relation to that approval, shall not apply in relation to any closed distribution system.

(2) Where the holder of a conveyance exemption who operates or has control of a closed distribution system receives an expression of interest from a customer who owns or occupies premises that are connected to the system, he must—

(a)inform that customer that the distribution system in question is a closed distribution system; and

(b)within 7 working days, beginning on the day on which he receives the expression of interest, by notice inform any third party supplier identified in the expression of interest that the distribution system in question is a closed distribution system.

(3) Where a customer has served an expression of interest in respect of a closed distribution system and—

(a)the customer, or a third party supplier identified in that expression of interest, serves a notice on the holder of the exemption relating to that distribution system requesting that the methodology for a proposed system charge be submitted to the Authority for approval; and

(b)at the time of receiving the request the holder of the exemption has not received any confirmation that the customer has entered into a contract with a third party, then paragraph (4) applies.

(4) From the time the holder of the conveyance exemption receives the request referred to in paragraph (3)(a), the conditions referred to in paragraph (1) shall have effect as if the distribution system in question were not a closed distribution system.

(5) Where a customer who owns or occupies premises that are connected to a closed distribution system has served a notice on the holder of a conveyance exemption relating to that system that he has entered into a contract with a third party supplier (“the confirmed third party supplier”) and—

(a)the customer or the confirmed third party supplier serves on the holder of the exemption a notice requesting that the methodology for use of the system charge that is being applied be submitted to the Authority for approval; and

(b)the methodology for calculating the charge has not previously been approved by the Authority,

paragraphs (6) to (11) apply.

(6) The holder of the exemption must, within 20 working days, beginning with the day on which he receives the request under paragraph (5)—

(a)provide the Authority with a charging statement in respect of the methodology for any system charge applied at the time the request was made and such other information or documents as the Authority may specify; and

(b)provide the customer and the confirmed third party supplier with a copy of that charging statement.

(7) Where the Authority has requested further documents or information in accordance with paragraph (6)(a) at a time when there are fewer than 10 working days remaining in the 20 working day period mentioned in that sub-paragraph, those further documents or information must be provided within 10 working days beginning with the day on which the holder of the exemption received the request for further documents or information.

(8) Where the holder of the exemption has complied with paragraph (6)(a), the Authority must as soon as is reasonably practicable—

(a)decide whether to approve the methodology set out in the charging statement; and

(b)notify the conveyance exemption holder and the confirmed third party supplier of its decision.

(9) Where the Authority does not approve the methodology, it must give reasons for that decision.

(10) Where the Authority has notified the holder of the exemption of a decision that it does not approve the methodology, that holder must not continue to impose a system charge except where the Authority has considered the methodology for such a charge and has approved it.

(11) Where the Authority has not approved a methodology submitted under paragraph (6), the holder of the exemption may—

(a)submit to the Authority a charging statement containing details of a revised methodology;

(b)provide the Authority with such other information and documents as the Authority may specify; and

(c)send a copy of the charging statement to the customer and the confirmed third party supplier.

(12) If the holder of the exemption takes the steps mentioned in paragraph (11), paragraphs (8) and (9) apply as if he had complied with paragraph (6).]

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.