48.—(1) If the whole or any part of a penalty is not paid by the date by which it is required to be paid, the unpaid balance from time to time shall carry interest at the rate for the time being prescribed under Article 127 of the Judgments Enforcement (Northern Ireland) Order 1981 (NI 6).

(2) If an application is made under paragraph (7) of Article 45 in relation to a penalty, the penalty is not required to be paid until the application has been determined.

(3) If the Authority grants an application under that paragraph in relation to a penalty but any portion of the penalty is not paid by the date specified in relation to it by the Authority under that paragraph, the Authority may where it considers it appropriate require so much of the penalty as has not already been paid to be paid immediately.

Modifications etc. (not altering text)

C1Art. 48 applied (with modifications) (3.7.2007) by Electricity Regulations (Northern Ireland) 2007 (S.R. 2007/321), regs. 1(1), 56(2) (with transitional provisions in Pt. IV)