PART VIIELECTRICITY FROM RENEWABLE SOURCES

F1Use of renewables obligation certificates issued in Great Britain54D

1

A renewables obligation order may provide that—

a

in such cases as may be specified in the order, and

b

subject to such conditions as may be so specified,

an electricity supplier may (to the extent provided for in accordance with the order) discharge his renewables obligation (or his obligation in relation to a particular period) by the production to the Authority of a Great Britain certificate.

2

In this Article “Great Britain certificate” means a certificate issued by the Great Britain authority in accordance with provision included, by virtue of section 32B of the Electricity Act 1989, in an order under section 32 of that Act (renewables obligations for Great Britain suppliers).