Search Legislation

The Planning Reform (Northern Ireland) Order 2006

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Section 9

 Help about opening options

Version Superseded: 01/04/2015

Alternative versions:

Status:

Point in time view as at 10/06/2006. This version of this provision has been superseded. Help about Status

Close

Status

You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.

Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.

Changes to legislation:

The Planning Reform (Northern Ireland) Order 2006, Section 9 is up to date with all changes known to be in force on or before 19 October 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

Power to decline to determine applicationsN.I.

This section has no associated Explanatory Memorandum

9.—(1) For Article 25A of the principal Order (power of Department to decline to determine applications) substitute—

Power to decline to determine subsequent application

25A.(1) The Department may decline to determine a relevant application if—

(a)any of the conditions in paragraphs (2) to (4) is satisfied; and

(b)the Department thinks there has been no significant change in the relevant considerations since the relevant event.

(2) The condition is that in the period of 2 years ending with the date on which the application mentioned in paragraph (1) is received the Department has refused a similar application under Article 31.

(3) The condition is that in that period the planning appeals commission has dismissed an appeal—

(a)against the refusal of a similar application; or

(b)under Article 33 in respect of a similar application.

(4) The condition is that—

(a)in that period the Department has refused more than one similar application; and

(b)there has been no appeal to the planning appeals commission against any such refusal.

(5) A relevant application is an application for planning permission for the development of any land.

(6) The relevant considerations are—

(a)the development plan so far as material to the application;

(b)any other material considerations.

(7) The relevant event is—

(a)for the purposes of paragraphs (2) and (4) the refusal of the similar application;

(b)for the purposes of paragraph (3) the dismissal of the appeal.

(8) An application for planning permission is similar to another application if (and only if) the Department thinks that the development and the land to which the applications relate are the same or substantially the same.

Power to decline to determine overlapping application

25AA.(1) The Department may decline to determine an application for planning permission for the development of any land which is made at a time when any of the conditions in paragraphs (2) to (4) applies in relation to a similar application.

(2) The condition is that a similar application is under consideration by the Department and the determination period for that application has not expired.

(3) The condition is that a similar application is under consideration by—

(a)the Department in pursuance of Article 31; or

(b)the planning appeals commission on an appeal under Article 32 or 33,

and the Department or, as the case may be, the planning appeals commission, has not issued its decision.

(4) The condition is that a similar application—

(a)has been granted by the Department;

(b)has been refused by the Department; or

(c)has not been determined by the Department within the determination period,

and the time within which an appeal could be made to the planning appeals commission under Article 32 or 33 has not expired.

(5) An application for planning permission is similar to another application if (and only if) the Department thinks that the development and the land to which the applications relate are the same or substantially the same.

(6) The determination period is—

(a)the period specified by the development order for the determination of the application; or

(b)such longer period as the applicant and the Department have agreed for the determination of the application..

(2) In Article 33(c) of the principal Order (appeal in default of planning decision), after “25A” insert “ or 25AA ”.

(3) After paragraph 4 of Schedule 1 to the principal Order (determination of applications for listed building consent) insert—

Power to decline to determine applicationN.I.

Power to decline to determine subsequent application

4A.(1) The Department may decline to determine an application for a relevant consent if—

(a)one or more of the conditions in sub-paragraphs (2) to (4) is satisfied; and

(b)the Department thinks there has been no significant change in any material considerations since the relevant event.

(2) The condition is that in the period of 2 years ending with the date on which the application mentioned in sub-paragraph (1) is received the Department has refused a similar application made under paragraph 1.

(3) The condition is that in that period the planning appeals commission has dismissed an appeal—

(a)against the refusal of a similar application; or

(b)under paragraph 8 in respect of a similar application.

(4) The condition is that—

(a)in that period the Department has refused more than one similar application; and

(b)there has been no appeal to the planning appeals commission against any such refusal.

(5) Relevant consent is—

(a)listed building consent; or

(b)consent under Article 51 (conservation area consent).

(6) The relevant event is—

(a)for the purposes of sub-paragraphs (2) and (4) the refusal of the similar application;

(b)for the purposes of sub-paragraph (3) the dismissal of the appeal.

(7) An application for relevant consent is similar to another application if (and only if) the Department thinks that the building and works to which the applications relate are the same or substantially the same.

(8) For the purposes of an application for consent under Article 51 (conservation area consent) a reference to a provision of this Order is a reference to that provision as excepted or modified by regulations under Article 51(5).

Power to decline to determine overlapping application

4B.(1) The Department may decline to determine an application for a relevant consent which is made at a time when any of the conditions in sub-paragraphs (2) to (4) applies in relation to a similar application.

(2) The condition is that a similar application is under consideration by the Department and the determination period for that application has not expired.

(3) The condition is that a similar application is under consideration by the planning appeals commission on an appeal under paragraph 7 or 8 and the commission has not issued its decision.

(4) The condition is that a similar application—

(a)has been granted by the Department;

(b)has been refused by the Department; or

(c)has not been determined by the Department within the determination period,

and the time within which an appeal could be made to the planning appeals commission under paragraph 7 or 8 has not expired.

(5) Relevant consent is—

(a)listed building consent; or

(b)consent under Article 51 (conservation area consent).

(6) An application for relevant consent is similar to another application if (and only if) the Department thinks that the building and works to which the applications relate are the same or substantially the same.

(7) The determination period is—

(a)the period prescribed for the determination of the application; or

(b)such longer period as the applicant and the Department have agreed for the determination of the application.

(8) For the purposes of an application for consent under Article 51 (conservation area consent) a reference to a provision of this Order is a reference to that provision as excepted or modified by regulations under Article 51(5)..

(4) In paragraph 8 of Schedule 1 to the principal Order (appeal in default of planning decision) after “decision on the application” insert “ or gives notice to the applicant that it has exercised its power under paragraph 4A or 4B to decline to determine the application ”.

(5) This Article has effect only in relation to applications made under the principal Order which are received by the Department after the coming into operation of this Article.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Northern Ireland Order in Council and provides information about its policy objective and policy implications. They aim to make the Order accessible to readers who are not legally qualified and accompany any Northern Ireland Order in Council made since 2002.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources