SCHEDULE 2
CROWN APPLICATION – TRANSITIONAL PROVISIONS
PART 1 PLANNING PERMISSION
Introduction
1.This Part applies to a development if—
2.In this Part— (a) the relevant date is the date...
Acceptable development
3.(1) This paragraph applies if before the relevant date in...
4.(1) This paragraph applies if before the relevant date the...
Pending proposals
5.(1) This paragraph applies if before the relevant date—
PART 2 LISTED BUILDINGS CONSENT AND CONSERVATION AREA CONSENT
Introduction
6.This Part applies to works if— (a) they are works...
7.In this Part— (a) the relevant date is the date...
Acceptable works
8.(1) This paragraph applies if before the relevant date in...
9.(1) This paragraph applies if before the relevant date the...
Pending proposals
10.(1) This paragraph applies if before the relevant date—
11.This Part shall have effect in relation to the demolition...
PART 3 HAZARDOUS SUBSTANCES
12.(1) This paragraph applies if at any time during the...