Forward work programme of the AuthorityN.I.
4.—(1) The Authority shall, before each financial year, publish a document (the “forward work programme”) containing a general description of the projects which it plans to undertake during the year in the exercise of its functions under this Order (other than projects comprising routine activities in the exercise of those functions).
(2) That description shall include the objectives of each project.
(3) The forward work programme for any year shall also include an estimate of the overall expenditure which the Authority expects to incur during the year in the exercise of its functions under this Order.
(4) The forward work programme prepared under this Article may, if the Authority so decides, be combined in a single programme with the forward work programme of the Authority prepared under Article 5 of the Energy Order.
(5) Before publishing the forward work programme for any year (other than one which is combined as mentioned in paragraph (4)), the Authority shall give notice—
(a)containing a draft of the forward work programme; and
(b)specifying the time within which representations or objections to the proposals contained in it may be made,
and shall consider any representations or objections which are duly made and not withdrawn.
(6) The notice under paragraph (5) shall be published by the Authority in such manner as it considers appropriate for the purpose of bringing the matters contained in it to the attention of persons likely to be affected by them.
(7) The Authority shall send a copy of any notice given by it under paragraph (5) to the Council and the Department.