The Scheme for Construction Contracts in Northern Ireland Regulations (Northern Ireland) 1999

Notice of intention to withhold payment

10.  Any notice of intention to withhold payment mentioned in Article 10 of the 1997 Order shall be given not later than 7 days before the final date for payment determined either in accordance with the construction contract, or where no such provision is made in the contract, in accordance with paragraph 8.