12. In this Part of this Schedule–N.I.
“determination date” means–
for an installation, part of an installation or mobile plant in relation to which a permit is granted, the date on which it is granted, whether in pursuance of the application for the permit or following an appeal;
for an installation, part of an installation or mobile plant in relation to which a permit is refused and the applicant for the permit appeals against the refusal, the date of the determination of the appeal refusing the permit;
for an installation, part of an installation or mobile plant in relation to which a permit is refused and no appeal is made against the refusal, the date immediately following the last day, determined in accordance with paragraph 2 of Schedule 9, on which notice of appeal might have been given;
“existing” means, in relation to a Part B or Part C installation or Part B or Part C mobile plant, an installation or mobile plant which is put into operation before the relevant date for that installation or mobile plant;
“new” means, in relation to a Part B or Part C installation or Part B or Part C mobile plant, an installation or mobile plant which is put into operation on or after the relevant date for that installation or mobile plant;
“relevant date” shall be interpreted in accordance with paragraphs 10 and 11.