Search Legislation

The Railways Infrastructure (Access, Management and Licensing of Railway Undertakings) Regulations (Northern Ireland) 2005

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: SCHEDULE 2

 Help about opening options

Version Superseded: 01/07/2009

Alternative versions:

Status:

Point in time view as at 03/01/2006.

Changes to legislation:

There are currently no known outstanding effects for the The Railways Infrastructure (Access, Management and Licensing of Railway Undertakings) Regulations (Northern Ireland) 2005, SCHEDULE 2. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Regulation 11

SCHEDULE 2N.I.ACCESS CHARGING

Principles of access chargingN.I.

1.—(1) The infrastructure manager must ensure that the application of the charging scheme—

(a)complies with the rules set out in the Network Statement produced in accordance with regulation 10; and

(b)results in equivalent and non-discriminatory charges for different railway undertakings that perform services of an equivalent nature in a similar part of the market.

(2) The calculation of the fee may in particular take into account the mileage, composition of the train and any specific requirements in terms of such factors as speed, axle load and the degree or period of utilisation of the infrastructure.

(3) Except where specific arrangements are made in accordance with paragraph 3, the infrastructure manager must ensure that the charging scheme in use is based on the same principles over the whole of his network.

(4) The charges for the minimum access package and track access to service facilities referred to in paragraphs 1 and 2 of Schedule 1 shall be set at the cost that is directly incurred as a result of operating the train service.

(5) Subject to sub-paragraph (6), the supply of services referred to in paragraph 2 of Schedule 1 shall not be subject to the principles set out in this paragraph.

(6) In setting the charge for the supply of services referred to in sub-paragraph (5), account must be taken of the competitive situation of rail transport.

(7) If the additional or ancillary services referred to in paragraphs 3 and 4 of Schedule 1 are offered by only one supplier the charge imposed for the supply of those services must relate to the cost of providing the service, calculated on the basis of the actual level of use.

(8) The infrastructure charge may include a charge to reflect the scarcity of capacity of the identifiable segment of the infrastructure during periods of congestion.

(9) The charges referred to in sub-paragraph (8) may be averaged over a reasonable spread of train services and times, but the relevant magnitudes of the infrastructure charges must be related to the costs attributable to the services.

Commencement Information

I1Sch. 2 para. 1 in operation at 3.1.2006, see reg. 1(1)

Exceptions to the charging principlesN.I.

2.—(1) In order to obtain full recovery of the costs incurred the infrastructure manager, with the approval of the Department under the access charges review may levy mark-ups on the basis of efficient, transparent and non-discriminatory principles, whilst guaranteeing optimum competitiveness, in particular in respect of international rail freight.

(2) The effect of sub-paragraph (1) must not be to exclude the use of infrastructure by market segments, which can pay at least the cost that is directly incurred as a result of operating the railway service, plus a rate of return which the market can bear.

(3) The charging system shall respect the productivity increases achieved by applicants.

Commencement Information

I2Sch. 2 para. 2 in operation at 3.1.2006, see reg. 1(1)

3.—(1) Subject to sub-paragraph (2), for specific investment projects completed—

(a)since 15th March 1988; or

(b)following the coming into operation of these Regulations,

the, infrastructure manager may set or continue to set higher charges on the basis of the long-term costs of the project.

(2) For sub-paragraph (1) to apply—

(a)the effect of the higher charges must be to increase the efficiency or cost-effectiveness of the project; and

(b)it must be the case that the project could not otherwise have been undertaken without the prospect of such higher charges.

(3) A charging arrangement to which sub-paragraph (1) applies may incorporate agreements on the sharing of the risk associated with new investments.

Commencement Information

I3Sch. 2 para. 3 in operation at 3.1.2006, see reg. 1(1)

4.—(1) The infrastructure manager’s average and marginal charges for equivalent uses of his infrastructure must be comparable and comparable services in the same market segment are subject to the same charges.

(2) The network statement produced by the infrastructure manager in accordance with regulation 10 must demonstrate that the charging system meets these requirements in so far as this can be done without the disclosure of commercially confidential information.

Commencement Information

I4Sch. 2 para. 4 in operation at 3.1.2006, see reg. 1(1)

5.  If the infrastructure manager intends to modify the essential elements of the charging system referred to in paragraph 2 that infrastructure manager must make such modifications public at least three months in advance of the modification taking effect.

Commencement Information

I5Sch. 2 para. 5 in operation at 3.1.2006, see reg. 1(1)

DiscountsN.I.

6.—(1) Subject to the provisions of articles 81, 82, 86 and 87 of the Treaty, and paragraph 1(2), any discount on the charges levied on a user of railway infrastructure by the infrastructure manager, for any service, must comply with the principles set out in this paragraph.

(2) Except where sub-paragraph (3) applies, discounts shall be limited to the actual saving of the administrative cost to the infrastructure manager and, in determining the level of discount to be applied, no account may be taken of cost savings already incorporated in the charge levied.

(3) The infrastructure manger may introduce schemes available to all users of the infrastructure, with reference to specified traffic flows, granting time limited discounts to encourage the development of new rail services, or encouraging the use of considerably under-utilised lines.

(4) The discounts available must be in accordance with the access charges review.

(5) Discounts may relate only to charges levied for a specified infrastructure section.

(6) Similar discount schemes must be applied to similar services.

Commencement Information

I6Sch. 2 para. 6 in operation at 3.1.2006, see reg. 1(1)

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources