Request to issue CHPGOsN.I.
4.—(1) A producer of electricity may request a CHPGO from the competent authority.
(2) A request may not be made for a CHPGO under paragraph (1) where the electricity is produced outside Northern Ireland.
(3) A request under paragraph (1) shall not be considered duly made until the competent authority is provided with all the information specified in Schedule 1 and the statement required under paragraph (4).
(4) The person making a request under paragraph (1) shall provide with the request a statement that in respect of the electricity which is the subject of the request—
(a)he is entitled to the issue of a CHPGO under these Regulation;
(b)he has not made and does not intend to make a request for a CHPGO in respect of the same electricity [F1to any person outside Northern Ireland] ; and
(c)he has not made and does not intend to make another request under paragraph (1) in respect of the same electricity.
Textual Amendments
F1Words in reg. 4(4)(b) substituted (31.12.2020) by The Guarantees of Origin of Electricity Produced from High-efficiency Cogeneration (Amendment) (EU Exit) Regulations 2018 (S.I. 2018/1206), regs. 1(3), 4(4); 2020 c. 1, Sch. 5 para. 1(1)
Commencement Information