5.—(1) Where the competent authority—
(a)Receives a request made in accordance with regulation 4(1); and
(b)Is satisfied that the electricity to which the request relates was produced from high-efficiency cogeneration; and
(c)Receives any charge payable under regulation 9;
The authority shall issue a CHPGO in respect of that electricity.
(2) A CHPGO shall be issued to the person making the request for it under Regulation 4(1) or such other person as that person may specify in the request.
(3) A CHPGO—
(a)shall contain the matters set out in Schedule 2; and
(b)may contain such other matters as the competent authority considers appropriate.
(4) Where a CHPGO has been issued in respect of any electricity and not revoked, a further CHPGO in respect of the same electricity shall not be issued by the competent authority.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: