The Renewable Heat Incentive Scheme Regulations (Northern Ireland) 2012

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: CHAPTER 1

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The Renewable Heat Incentive Scheme Regulations (Northern Ireland) 2012, CHAPTER 1. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

CHAPTER 1N.I.Ongoing obligations relating to the use of solid biomass to generate heat

InterpretationN.I.

27.  In this Part—

“energy content” means the energy contained within a substance (whether measured by a calorimeter or determined in some other way) expressed in terms of the substance’s gross calorific value within the meaning of British Standard BS 7420:1991 (Guide for determination of calorific values of solid, liquid and gaseous fuels (including definitions) published by the British Standards Institute on 28th June 1991);(1)

“landfill gas” means gas formed by the digestion of material in a landfill;

“standby generation” means the generation of electricity by equipment which is not used frequently or regularly to generate electricity and where all the electricity generated by that equipment is used by the accredited RHI installation;

“waste” has the same meaning as in Article 2(2) of the Waste and Contaminated Land (Northern Ireland) Order 1997(2)

Commencement Information

I1Reg. 27 in operation at 1.11.2012, see reg. 1

Participants using solid biomass contained in municipal wasteN.I.

28.—(1) This regulation applies to participants generating heat in an accredited RHI installation from solid biomass contained in municipal waste.

(2) The proportion of solid biomass contained in the municipal waste must be a minimum of 50 per cent.

(3) For the purposes of paragraph (2)—

(a)the proportion of solid biomass contained in the municipal waste is to be determined by the Department for every quarterly period;

(b)it is for the participant to provide, in such form as the Department may require, evidence to demonstrate to the Department’s satisfaction the proportion of the energy content of the municipal waste used in any quarterly period which is composed of fossil fuel, to enable the Department to determine the proportion of solid biomass in accordance with sub-paragraph (c);

(c)the proportion of solid biomass is the energy content of the municipal waste used in any quarterly period to generate heat less the energy content of any fossil fuel of which that municipal waste is in part composed, expressed as a percentage of the energy content of that municipal waste.

(4) The participant may use fossil fuel (other than fossil fuel mentioned in paragraph (3)(c)) in an accredited RHI installation for the following permitted ancillary purposes only—

(a)cleansing other fuels from the accredited RHI installation’s combustion system prior to using fossil fuel to heat the combustion system to its normal temperature;

(b)the heating of the accredited RHI installation’s combustion system to its normal operating temperature or the maintenance of that temperature;

(c)the ignition of fuels of low or variable calorific value;

(d)emission control;

(e)in relation to accredited RHI installations which are CHP systems, standby generation or the testing of standby generation capacity.

(5) The energy content of the fossil fuel used during any quarterly period for the permitted ancillary purposes specified in paragraph (4) must not exceed 10 per cent of the energy content of all the fuel used by that accredited RHI installation to generate heat during that quarterly period.

(6) Without prejudice to paragraph (3)(b), when determining the proportion of solid biomass contained in municipal waste, the Department may have regard to any information (whether or not produced to it by the participant) if, in its opinion, that information indicates what proportion of the energy content of the municipal waste is composed of fossil fuel.

(7) Subject to paragraph (8), where the participant produces to the Department—

(a)data published by the Department of the Environment or a district council demonstrating that the proportion of municipal waste used by that participant which is composed of fossil fuel is unlikely to exceed 50 per cent; and

(b)evidence that the municipal waste used has not been subject to any process before being used that is likely to have materially increased that proportion;

the Department may accept this as sufficient evidence for the purposes of paragraph (3)(b) of the fact that the proportion of the municipal waste used which is composed of fossil fuel is no more than 50 per cent.

(8) Where the Department so requests, the participant must arrange for samples of the municipal waste used (or to be used) in the accredited RHI installation, or of any gas or other substance produced as the result of the use of such municipal waste, to be taken by a person (and analysed in a manner) specified by the Department, and for the results of that analysis to be made available to the Department in such form as the Department may require.

(9) The participant may not generate heat using solid biomass contained in any waste other than municipal waste.

Commencement Information

I2Reg. 28 in operation at 1.11.2012, see reg. 1

Participants using solid biomass in accredited RHI installations with an installation capacity of between 45kWth and 1MWthN.I.

29.—(1) This regulation applies to participants generating heat from solid biomass, not being solid biomass contained in municipal waste, in an accredited RHI installation with an installation capacity of between 45kWth and 1MWth.

(2) The participant may use solid biomass contaminated with fossil fuel provided that the participant complies with the following sub-paragraphs as well as the other requirements of this regulation—

(a)the participant may use solid biomass contaminated with fossil fuel only where the proportion of fossil fuel contamination does not exceed 10 per cent;

(b)such contaminated biomass may not be used unless the fossil fuel is present because—

(i)the solid biomass has been subject to a process, the undertaking of which has caused the fossil fuel to be present in, on or with the biomass even though that was not the object of the process; or

(ii)the fossil fuel is waste and was not added to the solid biomass with a view to its being used as a fuel;

(c)for the purposes of sub-paragraph (a)—

(i)the proportion of fossil fuel contamination is to be determined by the Department for every quarterly period;

(ii)it is for the participant to provide, in such form as the Department may require, evidence to demonstrate to the Department’s satisfaction the proportion of fossil fuel contamination; and

(iii)the proportion of fossil fuel contamination is the energy content of the fossil fuel with which the solid biomass used in any quarterly period is contaminated expressed as a percentage of the energy content of all solid biomass (contaminated or otherwise) used in that quarterly period to generate heat other than fossil fuel used in accordance with sub-paragraphs (d) and (e);

(d)the participant may use fossil fuel (other than fossil fuel mentioned in sub-paragraph (a)) in an accredited RHI installation for the following permitted ancillary purposes only—

(i)cleansing other fuels from the accredited RHI installation’s combustion system prior to using fossil fuel to heat the combustion system to its normal temperature;

(ii)the heating of the accredited RHI installation’s combustion system to its normal operating temperature or the maintenance of that temperature;

(iii)the ignition of fuels of low or variable calorific value;

(iv)emission control;

(v)in relation to accredited RHI installations which are CHP systems, standby generation or the testing of standby generation capacity;

(e)the energy content of the fossil fuel used during a quarterly period for the permitted ancillary purposes specified in sub-paragraph (d) must not exceed 10 per cent of the energy content of all the fuel used by that accredited RHI installation to generate heat during that quarterly period.

(3) Where solid biomass contaminated with fossil fuel is used in an accredited RHI installation, the participant must keep and provide upon request written evidence including invoices, receipts and such other documentation as the Department may specify relating to fuel use and fossil fuel used for the permitted ancillary purposes specified in paragraph (2)(d) and provide this information upon request to the Department, in such form as the Department may require, to demonstrate compliance with this regulation.

(4) Without prejudice to paragraph (3), the Department may have regard to any information (whether or not produced to it by the participant) if, in its opinion, that information indicates what proportion of the contaminated solid biomass is composed of fossil fuel.

(5) Where—

(a)the Department is not satisfied that the proportion of fossil fuel contamination (within the meaning of paragraph 2(c)(iii) does not exceed 10 per cent; or

(b)the Department is not satisfied as to the matters specified in paragraphs (2)(d) and (2)(e),

the Department may require the participant to arrange for samples of the fuel used (or to be used) in the accredited RHI installation, or of any gas or other substance produced as the result of the use of such fuel, to be taken by a person (and analysed in a manner) specified by the Department, and for the results of that analysis to be made available to the Department in such form as the Department may require.

Commencement Information

I3Reg. 29 in operation at 1.11.2012, see reg. 1

(1)

ISBN 0580194825 Copies can be obtained from the British Standards Institution: www.bsi-global.com/en/

(2)

S.I. 1997/2778 (N.I. 19); Article 2(2) was amended by SR 2011 No. 127

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Rule and provides information about its policy objective and policy implications. They aim to make the Statutory Rule accessible to readers who are not legally qualified and accompany any Northern Ireland Statutory Rule or Draft Northern Ireland Statutory Rule laid before the UK Parliament during the suspension of the Northern Ireland Assembly.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources