Other eligibility requirements for technologiesN.I.
12.—(1) The requirements referred to in regulation 4(b) are—
(a)installation of the plant was completed and the plant was first commissioned on or after 1st September 2010;
(b)the plant was new at the time of installation;
(c)the plant uses liquid or steam as a medium for delivering heat to the space, liquid or process;
(d)heat generated by the plant is used for an eligible purpose.
(2) The requirements of paragraph (1)(a) and (b) are deemed to be satisfied where the plant was previously generating electricity only, using solid biomass or biogas, and was first commissioned as a CHP system on or after 1st September 2010;
(3) But the requirements of paragraph (1)(a) and (b) are not satisfied where the plant was previously generating heat only and was first commissioned as a CHP system on or after 1st September 2010.
Commencement Information
I1Reg. 12 in operation at 1.11.2012, see reg. 1