PART 4 Procedures on Receipt of Application
12.Application which appears to require determination as to need for environmental impact assessment
13.Subsequent application where environmental information previously provided
14.Subsequent application where environmental information not previously provided
16.Application referred to the Department under Section 29 without an environmental statement
17.Extension of the period for council’s or Department’s decision on an application for planning permission or subsequent application
PART 6 Coordination, Decision-making, Monitoring and Notification of Decisions
PART 9 Unauthorised EIA Development
33.Prohibition on the grant of planning permission or subsequent consent for unauthorised EIA development
34.Determination as to need for environmental statement, etc.
37.Procedure where the Commission receives an environmental statement
38.Further information and evidence respecting environmental statements
39.Publicity for environmental statements and decision making
1.Crude-oil refineries (excluding undertakings manufacturing only lubricants from crude oil)...
2.(a) Thermal power stations and other combustion installations with a...
3.(a) Installations for the reprocessing of irradiated nuclear fuel.
4.(a) Integrated works for the initial smelting of cast-iron and...
5.Installations for the extraction of asbestos and for the processing...
6.Integrated chemical installations, that is to say, installations for the...
7.(a) Construction of lines for long–distance railway traffic and of...
8.(a) Inland waterways and ports for inland–waterway traffic which permit...
9.Waste disposal installations for the incineration, chemical treatment (as defined...
10.Waste disposal installations for the incineration or chemical treatment (as...
11.Groundwater abstraction or artificial groundwater recharge schemes where the annual...
12.(a) Works for the transfer of water resources, other than...
13.Waste water treatment plants with a capacity exceeding 150,000 population...
14.Extraction of petroleum and natural gas for commercial purposes where...
15.Dams and other installations designed for the holding back or...
16.Pipelines with a diameter of more than 800 millimetres and...
17.Installations for the intensive rearing of poultry or pigs with...
18.Industrial plants for— (a) the production of pulp from timber...
19.Quarries and open–cast mining where the surface of the site...
20.Construction of overhead electrical power lines with a voltage of...
21.Installations for storage of petroleum, petrochemical or chemical products with...
22.Storage sites pursuant to Directive 2009/31/EC of the European Parliament...
23.Installations for the capture of carbon dioxide streams for the...
24.Any change to or extension of development listed in this...
Selection criteria referred to in Article 4.3 of the Directive
Matters for Inclusion in Environmental Statement
2.A description of the reasonable alternatives (for example in terms...
3.A description of the relevant aspects of the current state...
4.A description of the factors specified in regulation 5(2) likely...
5.A description of the likely significant effects of the development...
6.A description of the forecasting methods or evidence used to...
7.A description of the measures envisaged to avoid, prevent, reduce...
8.A description of the expected significant adverse effects of the...
9.A non–technical summary of the information provided under paragraphs 1...
10.A reference list detailing the sources used for the descriptions...