11.—(1) SEPA shall periodically review the conditions of permits and may do so at any time.
(2) Without prejudice to paragraph (1), a review of a permit shall be carried out where–
(a)the pollution caused by the installation or mobile plant covered by the permit is of such significance that the existing emission limit values of the permit need to be revised or new emission limit values need to be included in the permit;
(b)substantial changes in the best available techniques make it possible to reduce emissions from the installation or mobile plant significantly without imposing excessive costs; or
(c)the operational safety of the activities carried out in the installation or mobile plant requires other techniques to be used.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: