The works referred to in this Order and shown on the deposited plan are:–
Works No. 1 | Installation of a new intake headstock on the existing intake chamber located at Ordnance Survey National Grid Reference NG 7950 7080; provision of a new rose piece and sluice valve in that chamber; and refurbishment of that chamber and the provision of new covers. |
Works No. 2 | Installation of a new raw water pipe from the intake chamber to Works No. 3. |
Works No. 3 | Installation of a new meter chamber and meter to record flows, and the installation of a new swabbing chamber. |
Works No. 4 | Installation of a new concrete channel within the existing inlet channel; demolition of the existing channel situated downstream and excavation of the loch shoreline to merge into the new channel mouth; and installation of a baffle plate at the new channel mouth and a new stainless steel catch plate. |
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: