Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Scottish Statutory Instruments

2006 No. 465

ENVIRONMENTAL PROTECTION

The Environmental Noise (Scotland) Regulations 2006

Made

12th September 2006

Laid before the Scottish Parliament

13th September 2006

Coming into force

5th October 2006

The Scottish Ministers, in exercise of the powers conferred by section 2(2) of the European Communities Act 1972(1) and of all other powers enabling them in that behalf, hereby make the following Regulations:

PART 1SGENERAL

Citation, commencement and extentS

1.—(1) These Regulations may be cited as the Environmental Noise (Scotland) Regulations 2006 and shall come into force on 5th October 2006.

(2) These Regulations extend to Scotland only.

(3) Nothing in paragraph (2) means that strategic noise maps made or revised under these Regulations must be limited to Scotland.

Commencement Information

I1Reg. 1 in force at 5.10.2006, see reg. 1(1)

ApplicationS

2.—(1) These Regulations apply to environmental noise to which humans are exposed in particular in built up areas, in public parks or other quiet areas in an agglomeration, near schools, hospitals and other noise sensitive buildings and areas.

(2) These Regulations do not apply to noise that is caused by the person exposed to the noise, noise from domestic activities, noise created by neighbours, noise at work places or noise inside means of transport or due to military activities in military areas.

Commencement Information

I2Reg. 2 in force at 5.10.2006, see reg. 1(1)

InterpretationS

3.—(1) Unless otherwise defined in these Regulations, words and terms used in these Regulations and in the Directive shall have the meaning given in the Directive.

(2) In these Regulations–

“agglomeration” means an urbanised area having a population in excess of 100,000 people and a population density equal to or greater than 500 people per km2 and which is shown on a map or plan prepared and published by the Scottish Ministers in accordance with regulation 4;

“airport” means a civil airport;

“airport operator” means the person for the time being having, in relation to a particular airport, the management of that airport;

“calendar year” means a period of a year beginning on the 1st January;

“dB(A)” is a measure of sound pressure level (“A” weighted) in decibels as specified in British Standard BS EN 61672 2:2003(2);

“Directive” means Directive 2002/49/EC of the European Parliament and of the Council of 25th June 2002 relating to the assessment and management of environmental noise(3);

“first round agglomeration” means an urbanised area having a population in excess of 250,000 people and a population density equal to or greater than 500 people per km2 and which is shown on a map or plan prepared and published by the Scottish Ministers in accordance with regulation 4;

“first round major railway” means a railway having more than 60,000 train passages per year and which is shown on a map or plan prepared and published by the Scottish Ministers in accordance with regulation 4;

“first round major road” means a road having more than 6 million vehicle passages per year which is–

(a)

designated by the letter “A” followed by a number; or

(b)

a special road within the meaning of section 7 of the Roads (Scotland) Act 1984(4),

and which is shown on a map or plan prepared and published by the Scottish Ministers in accordance with regulation 4;

“Lday” has the meaning given in Article 3 and Annex I to the Directive and covers the period 0700 – 1900 hours in any 24 hour period;

“Levening” has the meaning given in Article 3 and Annex I to the Directive and covers the period 1900 – 2300 hours in any 24 hour period;

“Lnight” has the meaning given in Article 3 and Annex I to the Directive and covers the period 2300 – 0700 hours in any 24 hour period;

“Lden” has the meaning given in Article 3 and Annex I to the Directive;

“major airport” means a civil airport having more than 50,000 movements per year (a movement being a take off or a landing) excluding those purely for training purposes on light aircraft, and which is shown on a map or plan prepared and published by the Scottish Ministers in accordance with regulation 4;

“major road” means a road having more than 3 million vehicle passages per year which is–

(a)

designated by the letter “A” followed by a number; or

(b)

a special road within the meaning of section 7 of the Roads (Scotland) Act 1984,

and which is shown on a map or plan prepared and published by the Scottish Ministers in accordance with regulation 4;

“major railway” means a railway having more than 30,000 train passages per year and which is shown on a map or plan prepared and published by the Scottish Ministers in accordance with regulation 4;

“quiet area in an agglomeration” and “quiet area in a first round agglomeration” mean an area shown on a map or plan prepared and published by the Scottish Ministers in accordance with regulation 4.

Commencement Information

I3Reg. 3 in force at 5.10.2006, see reg. 1(1)

Maps identifying noise sources and quiet areasS

4.—(1) The Scottish Ministers shall prepare maps or plans showing–

(a)first round agglomerations;

(b)first round major roads;

(c)first round major railways;

(d)major airports;

(e)agglomerations;

(f)major roads;

(g)major railways; and

(h)quiet areas in first round agglomerations and in agglomerations.

(2) Every 5 years the Scottish Ministers–

(a)shall review maps or plans prepared pursuant to paragraph (1); and

(b)where they consider that such maps or plans are no longer appropriate, shall modify them as necessary.

(3) Certified copies of maps or plans prepared pursuant to paragraph (1) or modified pursuant to paragraph (2)–

(a)shall be made available for inspection at such times and in such places as the Scottish Ministers may determine, and information on when and where such copies may be inspected shall be published by the Scottish Ministers in such a manner as they may determine;

(b)may be published on a website and in such other manner as the Scottish Ministers consider appropriate; and

(c)shall be provided by the Scottish Ministers, on request and for a reasonable charge.

Commencement Information

I4Reg. 4 in force at 5.10.2006, see reg. 1(1)

PART 2SSTRATEGIC NOISE MAPS

CHAPTER 1SGENERAL REQUIREMENTS FOR STRATEGIC NOISE MAPS

Strategic noise maps: general requirementsS

5.—(1) Any strategic noise map made or revised under this Part shall satisfy the applicable requirements in Schedule 1.

(2) A competent authority under regulation 6 or 8 shall apply–

(a)the noise indicators Lden and night in accordance with Annex I to the Directive; and

(b)the supplementary noise indicators in all cases listed as examples in paragraph 3 of Annex I to the Directive,

when making or revising strategic noise maps under this Part.

(3) The values of Lden, night and the supplementary noise indicators shall be determined by means of the assessment methods set out in Schedule 2.

(4) Subject to paragraph (5) existing noise indicators and related data may be converted into Lden and night.

(5) The data referred to in paragraph (4) shall not be more than 3 years old.

(6) “Supplementary noise indicator” means a noise indicator as defined in Schedule 3.

Commencement Information

I5Reg. 5 in force at 5.10.2006, see reg. 1(1)

CHAPTER 2SSTRATEGIC NOISE MAPS – NOISE SOURCES OTHER THAN AIRPORTS

Application and Competent AuthorityS

6.  This Chapter does not apply to noise from airports and the competent authority for this Chapter is the Scottish Ministers.

Commencement Information

I6Reg. 6 in force at 5.10.2006, see reg. 1(1)

Duty to make, review and revise strategic noise mapsS

7.—(1) No later than 30th June 2007 the competent authority shall make and, in accordance with regulation 21, adopt strategic noise maps showing the situation in the preceding calendar year for all–

(a)first round agglomerations;

(b)first round major roads; and

(c)first round major railways.

(2) No later than 30th June 2012, and thereafter every 5 years, the competent authority shall make and, in accordance with regulation 21, adopt strategic noise maps showing the situation in the preceding calendar year for all–

(a)agglomerations;

(b)major roads; and

(c)major railways.

(3) Every 5 years, and whenever a major development occurs affecting the existing noise situation, the competent authority shall–

(a)review; and

(b)if necessary, revise

any strategic noise map made pursuant to paragraphs (1) or (2) and adopted pursuant to regulation 21.

Commencement Information

I7Reg. 7 in force at 5.10.2006, see reg. 1(1)

CHAPTER 3SSTRATEGIC NOISE MAPS – AIRPORTS

Application and Competent AuthorityS

8.  This Chapter applies to noise from airports and the competent authority for this Chapter is the airport operator.

Commencement Information

I8Reg. 8 in force at 5.10.2006, see reg. 1(1)

InterpretationS

9.—(1) In this Chapter–

“input data” means all the data and related information used to produce the numerical data in electronic form required by paragraph 3(2)(b) or 4(2)(b) (as appropriate) of Schedule 1;

“metadata” means such elements of Section 2 of the “SPIRE Data Standard, Version 1.0” (DEFRA, 25th November 2004)(5) as are required to describe the–

(a)

input data; and

(b)

information and data required by paragraph 3(2) or 4(2) (as appropriate) of Schedule 1.

(2) Any requirement in this Chapter to submit input data to the Scottish Ministers is a requirement to submit that input data in a format that–

(a)is electronic;

(b)allows electronic manipulation; and

(c)does not require manipulation in order to reproduce the numerical data in electronic form required by paragraph 3(2)(b) or 4(2)(b) (as appropriate) of Schedule 1.

Commencement Information

I9Reg. 9 in force at 5.10.2006, see reg. 1(1)

Duty to make, review and revise strategic noise maps: major airportsS

10.—(1) This regulation applies to major airports.

(2) No later than 31st March 2007, and thereafter every 5 years, the competent authority shall–

(a)make a strategic noise map showing the situation in the preceding calendar year for the airport; and

(b)submit that map with input data and metadata to the Scottish Ministers.

(3) Every 5 years, and whenever a major development occurs affecting the existing noise situation, the competent authority shall–

(a)review; and

(b)if necessary, revise

any strategic noise map made pursuant to paragraph (2) and adopted pursuant to regulation 21.

(4) The competent authority shall submit any strategic noise map revised pursuant to paragraph (3)(b), with input data and metadata, to the Scottish Ministers within 3 working days of its revision.

Commencement Information

I10Reg. 10 in force at 5.10.2006, see reg. 1(1)

Duty to make, review and revise strategic noise maps: other airportsS

11.—(1) This regulation applies to airports other than major airports.

(2) Where air traffic from the airport results in air traffic noise anywhere within a first round agglomeration, no later than 31st March 2007 the competent authority shall, in relation to that noise–

(a)make a strategic noise map showing the situation in the preceding calendar year for the first round agglomeration; and

(b)submit that map with input data and metadata to the Scottish Ministers.

(3) Where air traffic from the airport results in air traffic noise anywhere within an agglomeration, no later than 31st March 2012 and thereafter every 5 years, the competent authority shall, in relation to that noise–

(a)make a strategic noise map showing the situation in the preceding calendar year for the agglomeration; and

(b)submit that map with input data and metadata to the Scottish Ministers.

(4) Every 5 years, and whenever a major development occurs affecting the existing noise situation, the competent authority shall–

(a)review; and

(b)if necessary, revise

any strategic noise map made pursuant to paragraphs (2) or (3) and adopted pursuant to regulation 21.

(5) The competent authority shall submit any strategic noise map revised pursuant to paragraph (4)(b), with input data and metadata, to the Scottish Ministers within 3 working days of its revision.

Commencement Information

I11Reg. 11 in force at 5.10.2006, see reg. 1(1)

PART 3SACTION PLANS

CHAPTER 1SGENERAL

Duty to issue guidance on action plans and consolidated noise mapsS

12.—(1) No later than 18th July 2007 the Scottish Ministers shall issue guidance on the preparation and content of action plans.

(2) The Scottish Ministers shall compile a consolidated noise map comprising all strategic noise maps that are adopted from time to time pursuant to regulation 21.

Commencement Information

I12Reg. 12 in force at 5.10.2006, see reg. 1(1)

Action plans: general requirementsS

13.—(1) Any action plan drawn up or revised under this Part shall–

(a)meet the objectives of–

(i)preventing and reducing environmental noise where necessary and in particular where exposure levels can induce harmful effects on human health; and

(ii)preserving environmental noise quality where it is good;

(b)be designed to manage noise issues and effects, including noise reduction if necessary;

(c)aim to protect quiet areas in first round agglomerations and agglomerations, as appropriate, against an increase in noise;

(d)identify and address priorities for meeting the objectives set out in sub-paragraph (a);

(e)apply in particular to the most important areas as established by strategic noise maps adopted pursuant to regulation 21; and

(f)meet the requirements in Schedule 4.

(2) Paragraph (3) applies to–

(a)any action plan; and

(b)any revision of an action plan,

drawn up under this Part for a first round agglomeration or an agglomeration.

(3) Any action plan and any revision of an action plan shall be based upon and apply in particular to the most important areas as established by–

(a)all strategic noise maps that–

(i)are adopted pursuant to regulation 21; and

(ii)concern any part of the area addressed by the action plan; and

(b)a consolidated noise map compiled pursuant to regulation 12(2) to the extent that it concerns any part of the area addressed by the action plan.

Commencement Information

I13Reg. 13 in force at 5.10.2006, see reg. 1(1)

CHAPTER 2SACTION PLANS – NOISE SOURCES OTHER THAN AIRPORTS

Competent AuthorityS

14.  The competent authority for this Chapter is the Scottish Ministers.

Commencement Information

I14Reg. 14 in force at 5.10.2006, see reg. 1(1)

Duty to draw up, review and revise action plansS

15.—(1) No later than 18th July 2008 the competent authority shall draw up action plans for–

(a)places near first round major roads;

(b)places near first round major railways; and

(c)first round agglomerations.

(2) No later than 18th July 2013 the competent authority shall draw up action plans for–

(a)places near major roads;

(b)places near major railways; and

(c)agglomerations.

(3) Every 5 years, and whenever a major development occurs affecting the existing noise situation, the competent authority shall–

(a)review; and

(b)if necessary, revise,

action plans drawn up pursuant to paragraphs (1) or (2) and adopted pursuant to regulation 22.

Commencement Information

I15Reg. 15 in force at 5.10.2006, see reg. 1(1)

CHAPTER 3SACTION PLANS – AIRPORTS

Application and Competent AuthorityS

16.  This Chapter applies to noise from–

(a)major airports; and

(b)other airports where air traffic from the airport results in air traffic noise of an Lden value of 55 dB(A) or greater or an night value of 50 dB(A) or greater anywhere in first round agglomerations or agglomerations,

and the competent authority is the airport operator.

Commencement Information

I16Reg. 16 in force at 5.10.2006, see reg. 1(1)

Duty to draw up, review and revise action plansS

17.—(1) No later than 30th April 2008 the competent authority shall–

(a)draw up an action plan for places near the airport; and

(b)submit that action plan to the Scottish Ministers.

(2) If the competent authority was not required to draw up an action plan pursuant to paragraph (1), no later than 30th April 2013 the competent authority shall–

(a)draw up an action plan for places near the airport; and

(b)submit that action plan to the Scottish Ministers.

(3) Every 5 years, and whenever a major development occurs affecting the existing noise situation, the competent authority shall–

(a)review; and

(b)if necessary, revise,

action plans drawn up pursuant to paragraphs (1) or (2) and adopted pursuant to regulation 22.

(4) An action plan revised pursuant to paragraph (3) shall be submitted to the Scottish Ministers within 3 working days of its revision.

Commencement Information

I17Reg. 17 in force at 5.10.2006, see reg. 1(1)

CHAPTER 4SACTION PLANS – PUBLIC PARTICIPATION

Public participationS

18.  In preparing and revising action plans the competent authorities under regulations 14 and 16 shall ensure that–

(a)the public is consulted about proposals for action plans;

(b)the public is given early and effective opportunities to participate in the preparation and review of the action plans;

(c)the results of that public participation are taken into account;

(d)the public is informed of the decisions taken; and

(e)reasonable time frames are provided allowing sufficient time for each stage of public participation.

Commencement Information

I18Reg. 18 in force at 5.10.2006, see reg. 1(1)

CHAPTER 5SIMPLEMENTATION OF ACTION PLANS

Implementation of action plansS

19.—(1) Subject to paragraphs (2) and (3), where an action plan–

(a)has been adopted pursuant to regulation 22; and

(b)identifies a particular public authority as responsible for a particular action,

that public authority shall use all reasonable endeavours to take that action.

(2) Paragraph (1) shall not have effect where a public authority, other than the Scottish Ministers–

(a)provides the Scottish Ministers and the competent authority (if not the Scottish Ministers) responsible for preparation of the action plan with written reasons for being unable to take the action for which it has been designated as responsible; and

(b)it publishes those reasons.

(3) Paragraph (1) shall not have effect where the Scottish Ministers–

(a)are the public authority identified in an action plan as responsible for a particular action; and

(b)publish reasons for being unable to take the action for which they have been identified as responsible.

(4) In this regulation “public authority” includes any person who exercises functions of a public nature, but does not include–

(a)the Scottish Parliament or a person exercising functions in connection with proceedings in the Scottish Parliament; or

(b)any person discharging or purporting to discharge any responsibilities of a judicial nature vested in that person, or a person discharging responsibilities in connection with the execution of judicial process.

Commencement Information

I19Reg. 19 in force at 5.10.2006, see reg. 1(1)

PART 4SCOOPERATION WITH EXTERNAL COMPETENT AUTHORITIES

Co operation with external competent authoritiesS

20.—(1) A competent authority under these Regulations (which shall include the Scottish Ministers for the purposes of their functions under Part 5 of these Regulations) shall co operate with an external competent authority–

(a)when necessary in order to meet its obligations under these Regulations; or

(b)when requested to do so by an external competent authority in relation to obligations arising under the Directive.

(2) In this Part “external competent authority” means a competent authority designated in relation to England, Northern Ireland, or Wales for the purposes of Article 4 of the Directive.

Commencement Information

I20Reg. 20 in force at 5.10.2006, see reg. 1(1)

PART 5SADOPTION OF STRATEGIC NOISE MAPS AND ACTION PLANS

Adoption of strategic noise mapsS

21.—(1) If the Scottish Ministers consider that a strategic noise map–

(a)submitted to them pursuant to regulation 10 or 11;

(b)submitted to them pursuant to paragraph (4); or

(c)made or revised by them,

meets the requirements of regulation 5, they shall adopt the map.

(2) If the Scottish Ministers consider that a strategic noise map submitted to them pursuant to regulation 10 or 11 or paragraph (4) does not meet the requirements of regulation 5 they shall–

(a)amend and adopt the map; or

(b)reject the map.

(3) If a strategic noise map is rejected pursuant to paragraph (2)(b) the Scottish Ministers shall notify the competent authority that submitted it of–

(a)the reasons why the map was not adopted; and

(b)the date by which the map shall be revised and resubmitted.

(4) The recipient of a notification under paragraph (3) shall submit the revised strategic noise map to the Scottish Ministers by the date specified in the notification.

(5) If the Scottish Ministers amend a strategic noise map–

(a)submitted to them pursuant to regulation 10 or 11; or

(b)submitted to them pursuant to paragraph (4),

they shall take such steps as they consider appropriate for ensuring that the map complies with the requirements of regulation 5.

Commencement Information

I21Reg. 21 in force at 5.10.2006, see reg. 1(1)

Adoption of action plansS

22.—(1) If the Scottish Ministers consider that an action plan–

(a)submitted to them pursuant to regulation 17(1)(b), 17(2)(b) or 17(4);

(b)submitted to them pursuant to paragraph (5); or

(c)drawn up or revised by them,

meets the requirements of regulation 13, they may adopt the action plan.

(2) Paragraph (3) applies if–

(a)the Scottish Ministers consider that an action plan submitted to them pursuant to regulation 17(1)(b), 17(2)(b) or 17(4) does not meet the requirements of regulation 13; or

(b)an action plan is not adopted pursuant to paragraph (1).

(3) Where this paragraph applies the Scottish Ministers shall–

(a)amend and adopt the plan; or

(b)reject the plan.

(4) If an action plan is rejected pursuant to paragraph (3)(b) the Scottish Ministers shall notify the competent authority that submitted it of–

(a)the reasons why the plan was not adopted; and

(b)the date by which the plan shall be revised and resubmitted.

(5) The recipient of a notification under paragraph (4) shall submit the revised action plan to the Scottish Ministers by the date specified in the notification.

(6) If the Scottish Ministers amend an action plan–

(a)submitted to them pursuant to regulation 17(1)(b), 17(2)(b) or 17(4); or

(b)submitted to them pursuant to paragraph (5),

they shall take such steps as they consider appropriate for ensuring that the action plan complies with the requirements of these Regulations.

Commencement Information

I22Reg. 22 in force at 5.10.2006, see reg. 1(1)

PART 6SPOWERS OF THE SCOTTISH MINISTERS IN RELATION TO THE FUNCTIONS OF OTHER COMPETENT AUTHORITIES

ApplicationS

23.  This Part applies to any functions under these Regulations exercised by a competent authority other than the Scottish Ministers.

Commencement Information

I23Reg. 23 in force at 5.10.2006, see reg. 1(1)

Powers of the Scottish MinistersS

24.—(1) The Scottish Ministers may at any time require a competent authority to provide information in relation to its functions under these Regulations.

(2) A request for information pursuant to paragraph (1)–

(a)shall be made in writing;

(b)may specify the format in which information shall be provided; and

(c)may specify the period of time within which a response shall be received.

(3) If a competent authority receives a request pursuant to paragraph (1) it shall respond–

(a)within the time period specified pursuant to paragraph (2)(c); or

(b)if no such period is specified, within 14 days of receipt of the request.

(4) Where–

(a)the Scottish Ministers have consulted the competent authority; and

(b)they consider that by reason of any act or omission, or any likely act or omission, by the competent authority–

(i)a requirement of these Regulations; or

(ii)a requirement imposed on the United Kingdom by the Directive,

is unlikely to be met, the Scottish Ministers may exercise such of the functions of the competent authority as they consider appropriate.

Commencement Information

I24Reg. 24 in force at 5.10.2006, see reg. 1(1)

Recovery of expensesS

25.—(1) Where the Scottish Ministers incur expenses pursuant to–

(a)regulation 21(2);

(b)regulation 22(3);

(c)regulation 24(1); or

(d)regulation 24(4),

they may recover those expenses from the relevant competent authority.

(2) In this regulation “relevant competent authority” means–

(a)in relation to regulation 21(2), the competent authority that submitted the strategic noise map pursuant to regulation 10 or 11;

(b)in relation to regulation 22(3), the competent authority that submitted the action plan pursuant to regulation 17;

(c)in relation to regulation 24(1), the competent authority required to provide information to the Scottish Ministers pursuant to that regulation; and

(d)in relation to regulation 24(4), the competent authority whose functions the Scottish Ministers exercise pursuant to that regulation.

Commencement Information

I25Reg. 25 in force at 5.10.2006, see reg. 1(1)

PART 7SINFORMATION TO THE PUBLIC AND GUIDANCE

Availability of strategic noise maps, consolidated noise maps and action plansS

26.—(1) Any–

(a)strategic noise map that is made available to the public before it is adopted pursuant to regulation 21; or

(b)action plan that is made available to the public before it is adopted pursuant to regulation 22,

shall include prominently displayed wording identifying it as a draft subject to adoption by the Scottish Ministers.

(2) Any–

(a)strategic noise map adopted pursuant to regulation 21;

(b)consolidated noise map compiled pursuant to regulation 12(2); or

(c)action plan adopted pursuant to regulation 22,

shall be published by the Scottish Ministers in accordance with the requirements of paragraph (3).

(3) Any strategic noise map, consolidated noise map or action plan published pursuant to paragraph (2) shall be accompanied by a summary setting out the most important points.

(4) Certified copies of such strategic noise maps, consolidated noise maps and action plans–

(a)shall be made available for inspection at such times and in such places as the Scottish Ministers may determine, and information on when and where such copies may be inspected shall be published by the Scottish Ministers in such a manner as they may determine;

(b)may be published on a website and in such other manner as the Scottish Ministers consider appropriate; and

(c)shall be provided by the Scottish Ministers, on request and for a reasonable charge.

Commencement Information

I26Reg. 26 in force at 5.10.2006, see reg. 1(1)

GuidanceS

27.—(1) The Scottish Ministers may from time to time issue such guidance as they consider appropriate in relation to the operation of these Regulations.

(2) Any person having functions under these Regulations shall have regard to such guidance.

Commencement Information

I27Reg. 27 in force at 5.10.2006, see reg. 1(1)

RHONA BRANKIN

Authorised to sign by the Scottish Ministers

St Andrew’s House,

Edinburgh

Regulations 5 and 9

SCHEDULE 1SMINIMUM REQUIREMENTS FOR STRATEGIC NOISE MAPPING

InterpretationS

1.  In this Schedule–

“editable” means in a format that allows (without the need for manipulation) the electronic production of–

(a)

numerical data in tables; and

(b)

graphical plots,

to display the information described in paragraphs 1.5, 1.6, 1.7, 2.5, 2.6 and 2.7 of Annex VI to the Directive;

“grid” means a grid of vector points which are–

(a)

at 10 metre by 10 metre intervals;

(b)

spatially referenced to the British National Grid reference system used by the Ordnance Survey as a pair of integers to show Eastings then Northings in metres from the origin; and

(c)

aligned with the 10 metre vertices of the British National Grid reference system used by the Ordnance Survey so that references finish with the number 0.

Commencement Information

I28Sch. 1 para. 1 in force at 5.10.2006, see reg. 1(1)

General requirements for strategic noise mapsS

2.—(1) Strategic noise maps and their revisions shall–

(a)satisfy the minimum requirements laid down in Annex IV to the Directive; and

(b)be clear and comprehensible.

(2) In applying sub-paragraph (1)(a) any reference in Annex IV to the Directive to–

(a)Article 8 of the Directive shall be taken to be a reference to regulations 13, 15 and 17 of these Regulations;

(b)Article 9 of the Directive shall be taken to be a reference to regulation 26 of these Regulations.

Commencement Information

I29Sch. 1 para. 2 in force at 5.10.2006, see reg. 1(1)

Requirements for strategic noise maps for agglomerationsS

3.—(1) This paragraph applies only to–

(a)a strategic noise map made under regulation 7(1)(a), 7(2)(a), 11(2) or 11(3); or

(b)a revision of such a strategic noise map.

(2) Strategic noise maps shall–

(a)include the information (in electronic format) described in paragraphs 1.1 to 1.4 inclusive of Annex VI to the Directive; and

(b)include editable numerical data in electronic form containing the values of Lden, night and the supplementary noise indicators on a grid.

Commencement Information

I30Sch. 1 para. 3 in force at 5.10.2006, see reg. 1(1)

Requirements for strategic noise maps for major roads, major railways and major airportsS

4.—(1) This paragraph applies only to–

(a)any strategic noise map made under–

(i)regulation 7(1)(b) or (c),

(ii)regulation 7(2)(b) or (c),

(iii)regulation 10(2); or

(b)any revision of such a map.

(2) Strategic noise maps shall–

(a)include the information (in electronic format) described in paragraphs 2.1 to 2.4 inclusive of Annex VI to the Directive; and

(b)include editable numerical data in electronic form containing the values of Lden, night and the supplementary noise indicators on a grid.

Commencement Information

I31Sch. 1 para. 4 in force at 5.10.2006, see reg. 1(1)

Regulation 5

SCHEDULE 2SASSESSMENT METHODS FOR THE NOISE INDICATORS

IntroductionS

1.—(1) The values of Lden, night and the supplementary noise indicators shall be determined by computation (at the assessment position).

(2) In this Schedule–

“assessment position” means the assessment height in paragraph 7 of Annex IV to the Directive; and

“Recommendation” means Commission Recommendation 2003/613/EC of 6th August 2003 concerning the guidelines on the revised interim computation methods for industrial noise, aircraft noise, road traffic noise and railway noise, and related emissions data(6).

Commencement Information

I32Sch. 2 para. 1 in force at 5.10.2006, see reg. 1(1)

Assessment method for road traffic noise indicatorsS

2.  For road traffic noise indicators the assessment method “Calculation of road traffic noise” (Department of Transport, 7th June 1988, HMSO)(7) shall be used, adapted using the report “Method for converting the UK road traffic noise index LA10,18h to the EU noise indices for road noise mapping” (DEFRA, 24th January 2006)(8).

Commencement Information

I33Sch. 2 para. 2 in force at 5.10.2006, see reg. 1(1)

Assessment method for railway noise indicatorsS

3.  For railway noise indicators the assessment methods–

(a)“Calculation of railway noise” (Department of Transport, 13th July 1995, HMSO)(9); and

(b)(in relation to railways to which it is expressed to apply) “Calculation of railway noise 1995 Supplement No. 1 Procedure for the calculation of noise from Eurostar trains class 373” (Department for Transport, 20th October 1996, Stationery Office)(10),

shall be used, adapted as shown in Figure 6.5 of the report “Rail and wheel roughness – implications for noise mapping based on the Calculation of Railway Noise procedure” (DEFRA, March 2004)(11).

Commencement Information

I34Sch. 2 para. 3 in force at 5.10.2006, see reg. 1(1)

Assessment methods for aircraft noise indicatorsS

4.  For aircraft noise indicators the assessment method “Report on Standard Method of Computing Noise Contours around Civil Airports” (Second Edition, European Civil Aviation Conference, 2 3 July 1997)(12) shall be used in accordance with paragraph 2.4 of the Annex to the Recommendation.

Commencement Information

I35Sch. 2 para. 4 in force at 5.10.2006, see reg. 1(1)

Assessment methods for industrial noise indicators and port noise indicatorsS

5.—(1) For industrial noise indicators and port noise indicators the propagation assessment method described in “ISO 9613 2:1996 Acoustics – Attenuation of sound during propagation outdoors – Part 2: General method of calculation” (International Standards Organisation, 1996)(13) shall be used in accordance with paragraph 2.5 of the Annex to the Recommendation.

(2) Suitable noise emission data (input data) for “ISO 9613 2:1996 Acoustics – Attenuation of sound during propagation outdoors – Part 2: General method of calculation” can be obtained either from measurements carried out in accordance with one of the following methods:

(a)“Acoustics. Determination of sound power levels of multisource industrial plants for evaluation of sound pressure levels in the environment. Engineering method” (BS ISO 8297:1994, British Standards Institute)(14);

(b)“Acoustics. Determination of sound power levels of noise sources using sound pressure. Engineering method in an essentially free field over a reflecting plane” (BS EN ISO 3744:1995, British Standards Institute)(15);

(c)“Acoustics. Determination of sound power levels of noise sources using sound pressure. Survey method using an enveloping measurement surface over a reflecting plane” (BS EN ISO 3746:1996, British Standards Institute)(16),

or by using Toolkit 10 of the “Good Practice Guide for Strategic Noise Mapping and the Production of Associated Data on Noise Exposure Version 2, Position Paper Final Draft” (European Commission Working Group Assessment of Exposure to Noise, 13th January 2006)(17).

Commencement Information

I36Sch. 2 para. 5 in force at 5.10.2006, see reg. 1(1)

Regulation 5

SCHEDULE 3SSUPPLEMENTARY NOISE INDICATORS

InterpretationS

1.  In this Schedule–

  • “LA10,18h” is the arithmetic mean noise level in dB(A) exceeded for 10% of each hour over the period 06:00 24:00 hours;

  • “LAeq,16h” is the equivalent continuous sound level in dB(A) that, over the period 07:00 – 23:00 hours, contains the same sound energy as the actual fluctuating sound that occurred in that period;

  • “LAeq,18h” is the equivalent continuous sound level in dB(A) that, over the period 06:00 – 24:00 hours, contains the same sound energy as the actual fluctuating sound that occurred in that period; and

  • “LAeq,6h” is the equivalent continuous sound level in dB(A) that, over the period 24:00 – 06:00 hours, contains the same sound energy as the actual fluctuating sound that occurred in that period.

Commencement Information

I37Sch. 3 para. 1 in force at 5.10.2006, see reg. 1(1)

Road Traffic NoiseS

2.  The supplementary noise indicators in relation to road traffic noise are–

(a)LA10,18h;

(b)LAeq,16h;

(c)Lday; and

(d)Levening.

Commencement Information

I38Sch. 3 para. 2 in force at 5.10.2006, see reg. 1(1)

Railway NoiseS

3.  The supplementary noise indicators in relation to railway noise are–

(a)LAeq,16h;

(b)LAeq,18h;

(c)LAeq,6h;

(d)Lday; and

(e)Levening.

Commencement Information

I39Sch. 3 para. 3 in force at 5.10.2006, see reg. 1(1)

Aircraft NoiseS

4.  The supplementary noise indicators in relation to aircraft noise are–

(a)LAeq,16h;

(b)Lday; and

(c)Levening.

Commencement Information

I40Sch. 3 para. 4 in force at 5.10.2006, see reg. 1(1)

Industrial Noise and Port NoiseS

5.  The supplementary noise indicators in relation to industrial noise and port noise are–

(a)LAeq,16h;

(b)Lday; and

(c)Levening.

Commencement Information

I41Sch. 3 para. 5 in force at 5.10.2006, see reg. 1(1)

Regulation 13

SCHEDULE 4SMINIMUM REQUIREMENTS FOR ACTION PLANS

GeneralS

1.—(1) An action plan shall–

(a)meet the minimum requirements of Annex V to the Directive;

(b)contain a summary covering all the important aspects referred to in Annex V to the Directive, not exceeding 10 pages in length; and

(c)be clear and comprehensible.

(2) In applying sub-paragraph (1) any reference in Annex V to the Directive to–

(a)Article 5 of the Directive shall be taken to be a reference to regulation 5 of these Regulations;

(b)Article 8(7) of the Directive shall be taken to be a reference to regulation 18 of these Regulations.

Commencement Information

I42Sch. 4 para. 1 in force at 5.10.2006, see reg. 1(1)

Explanatory Note

(This note is not part of the Regulations)

These Regulations implement Directive 2002/49/EC of the European Parliament and of the Council of 25 June 2002 relating to the assessment and management of environmental noise (O.J. No. L 189, 18.07.02, p. 12) (“the Directive”). They extend to Scotland only.

Regulation 4 requires the Scottish Ministers to prepare maps or plans showing the noise sources for which strategic noise maps shall be made, and showing quiet areas in first round agglomerations and in agglomerations. Regulation 7 requires the Scottish Ministers to make strategic noise maps for agglomerations, major roads and major railways for noise sources other than airports. Every 5 years and whenever a major development occurs, the Scottish Ministers shall review (and if necessary, revise) those strategic noise maps.

Regulations 10 and 11 require airport operators to make strategic noise maps for airports. Strategic noise maps shall be made for: (i) all major airports; and (ii) air traffic noise in agglomerations arising from other airports. Those strategic noise maps shall be reviewed (and revised if necessary) every 5 years and whenever a major development occurs. Once made, strategic noise maps (or their revisions) shall be submitted to the Scottish Ministers for adoption.

All strategic noise maps shall meet the requirements set out in regulation 5.

Regulation 5 and Schedule 3 specify which noise indicators and supplementary noise indicators shall be used in making the strategic noise maps. Schedule 2 sets out the assessment methods to be used in calculating the values of noise indicators. Different methods are specified for each noise source.

Regulation 12 requires the Scottish Ministers to publish guidance on the preparation and content of action plans. It also requires the Scottish Ministers to compile and publish a consolidated noise map.

Regulation 13 sets out the requirements for action plans.

Regulation 15 requires the Scottish Ministers to draw up action plans for places near to major roads and major railways, and for first round agglomerations and agglomerations. The Scottish Ministers shall review (and revise, if necessary) such action plans every 5 years, or sooner if a major development occurs.

Regulation 17 requires airport operators to draw up action plans in relation to major airports and other airports (if air traffic noise from those airports results in a value of 55 Lden or 50 night anywhere in agglomerations). The airport operator shall review (and revise, if necessary) such action plans every 5 years, or sooner if a major development occurs. Once drawn up or revised, action plans shall be submitted to the Scottish Ministers for adoption.

Regulation 18 specifies the public participation required during the preparation and revision of action plans.

Regulation 19 requires public authorities to use all reasonable endeavours to take actions for which they have been identified as responsible in action plans. Where they are unable to take such actions, they shall provide written reasons for being unable to do so.

Regulation 20 requires competent authorities in Scotland to co-operate with their counterparts in England, Northern Ireland and Wales when necessary to do so in order to meet obligations under these Regulations or the Directive.

Regulations 21 and 22 set out the mechanism by which the Scottish Ministers adopt strategic noise maps and action plans respectively.

Regulation 24 provides the Scottish Ministers with the power to require competent authorities to provide information in relation to their functions under the Regulations or to step in and carry out the functions of competent authorities under specified circumstances.

Regulation 25 gives the Scottish Ministers power to reclaim certain expenses from competent authorities.

Regulation 26 sets out requirements for the publication of consolidated noise maps compiled by and strategic noise maps and action plans approved by the Scottish Ministers.

Regulation 27 gives the Scottish Ministers power to issue guidance relating to the operation of the Regulations, and requires any person having functions under the Regulations to have regard to such guidance.

A Regulatory Impact Assessment has been prepared and placed in the library of the Scottish Parliament. A copy can be obtained from the Climate Change and Air Division, Scottish Executive Environment and Rural Affairs Department (SEERAD), Victoria Quay, Leith, Edinburgh, EH6 6QQ.

(1)

1972 c. 68. Section 2(2) of the 1972 Act was amended by the Scotland Act 1998 (c. 46), Schedule 8 paragraph 15(3). The function conferred on the Minister of the Crown was, in so far as within devolved competence, transferred to the Scottish Ministers by virtue of section 53 of the Scotland Act 1998.

(2)

ISBN 0-580-42224-0.

(3)

O.J. No. L 189, 18.07.02, p.12.

(4)

1984 c. 54. There are amendments to section 7 not relevant to these Regulations.

(5)

SPIRE Programme, Product Reference: SIP–DP– 011.

(6)

O.J. No. L 212, 22.8.03, p.49.

(7)

ISBN 0115508473.

(8)

Prepared by TRL Limited and Casella Stanger, Document Reference st/05/91/AGG04442.

(9)

ISBN 0115517545.

(10)

ISBN 0115518738.

(11)

Prepared by AEA Technology plc, Document Reference: AEATR-PC&E-2003-002.

(12)

Adopted by the Twenty-First Plenary Session of ECAC, Document Reference: ECAC.CEAC Doc. 29.

(13)

International Organisation for Standardization ().

(17)

European Commission Working Group Assessment of Exposure to Noise (http://www.defra.gov.uk/environment/noise/mapping/exposure/pdf/exposuredata-guide.pdf).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Executive Note

Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources