The Renewables Obligation (Scotland) Order 2009

[F1Generating stations using excluded capacity to generate electricity

This section has no associated Executive Note

17AB.(1) This article applies to a generating station where excluded capacity forms all or part of the total installed capacity of the station.

(2) SROCs are not to be issued in respect of any electricity generated in any month by a generating station to which this article applies unless during that month—

(a)all of the electricity generated by the station using the excluded capacity is measured separately from any electricity generated by the station using RO capacity; or

(b)all of the electricity generated by the station using the RO capacity is measured separately from any electricity generated by the station using the excluded capacity.

(3) SROCs are not to be issued in respect of any electricity generated using excluded capacity.]

Textual Amendments