PART 6Banding and grandfathering
F1High-range co-firing in the 2013/14 obligation period28A
1
This article applies to electricity which is generated—
a
before 1st April 2014;
b
in the way described as “high-range co-firing” in Schedule 2; and
c
by a generating station to which article 29 does not apply.
2
Subject to paragraph (4), the amount of electricity to be stated in each SROC issued in respect of electricity to which this article applies is of a megawatt hour.
3
Paragraph (4) applies to electricity to which this article applies which is generated—
a
in the way described as “high-range co-firing with CHP” in Schedule 2; and
b
using—
i
pre-2013 capacity; or
ii
2013/15 capacity in respect of which a declaration has been made in accordance with article 28(7).
4
Where this paragraph applies, the amount of electricity to be stated in each SROC is—
a
in respect of the qualifying proportion of the electricity to which this paragraph applies, of a megawatt hour; and
b
in respect of the remainder of the electricity to which this paragraph applies, of a megawatt hour.
5
This article is subject to article 32.