xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

PART 6Banding and grandfathering

[F1High-range co-firing in the 2013/14 obligation period

28A.(1) This article applies to electricity which is generated—

(a)before 1st April 2014;

(b)in the way described as “high-range co-firing” in Schedule 2; and

(c)by a generating station to which article 29 does not apply.

(2) Subject to paragraph (4), the amount of electricity to be stated in each SROC issued in respect of electricity to which this article applies is of a megawatt hour.

(3) Paragraph (4) applies to electricity to which this article applies which is generated—

(a)in the way described as “high-range co-firing with CHP” in Schedule 2; and

(b)using—

(i)pre-2013 capacity; or

(ii)2013/15 capacity in respect of which a declaration has been made in accordance with article 28(7).

(4) Where this paragraph applies, the amount of electricity to be stated in each SROC is—

(a)in respect of the qualifying proportion of the electricity to which this paragraph applies, of a megawatt hour; and

(b)in respect of the remainder of the electricity to which this paragraph applies, of a megawatt hour.

(5) This article is subject to article 32.]

Textual Amendments