PART 6Banding and grandfathering

Generating stations which were accredited as at 11th July 2006

30.[F1(1) This article applies to electricity which is generated—

(a)by a generating station—

(i)which was accredited as at 11th July 2006;

(ii)which has not ceased to be accredited since that date; and

(iii)to which article 29 does not apply;

(b)using pre-2013 capacity; and

(c)in one of the ways described in the first column of Part 3 of Schedule 2.]

F2(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

[F3(3) The amount of electricity to be stated in each SROC issued in respect of electricity to which this article applies is (subject to paragraphs (4) to (6)) the amount in the second column of Part 3 of Schedule 2 which corresponds to the description in the first column of that Part of that Schedule of the way in which the electricity was generated.]

(4) Where, at the time it generates the electricity, the generating station's total installed capacity is greater than it was on 11th July 2006, paragraph (3) applies only in relation to SROCs which are to be issued in respect of–

(a)where electricity generated using the total installed capacity of the station as at 11th July 2006 (“the original capacity”) is measured separately from electricity generated using capacity which has been added to the station since that date (“additional capacity”), the electricity [F4to which this article applies] which is generated using the station's original capacity;

[F5(b)in any other case, the appropriate percentage of the electricity to which this article applies (the appropriate percentage for these purposes being the total installed capacity of the station as at 11th July 2006 expressed as a percentage of the total installed capacity of the pre-2013 capacity of the station as at the date of generation of the electricity).]

(5) In relation to the remainder of the electricity [F6to which this article applies], the amount of electricity to be stated in each SROC is to be determined in accordance with article 27(4)F7... except to the extent that the electricity–

(a)is generated using additional capacity which was operational before 1st April 2011 (“relevant additional capacity”); and

(b)is generated in a way described in the first column of Part 4 of Schedule 2.

(6) Where the electricity [F8to which this article applies] is generated using relevant additional capacity in a way described in the first column of Part 4 of Schedule 2, the amount of electricity to be stated in each SROC which is to be issued in respect of that electricity is the amount which corresponds to that description in the second column of that Part of that Schedule.

(7) In paragraphs (5) and (6), the reference to electricity being generated using relevant additional capacity is a reference to–

(a)where electricity generated using relevant additional capacity is measured separately from electricity generated otherwise than by using such capacity, the electricity which is generated using that capacity;

(b)in any other case, the appropriate percentage of the electricity [F9to which this article applies] (the appropriate percentage for these purposes being the relevant additional capacity of the station at the date of generation of the electricity expressed as a percentage of the [F10total installed capacity of the pre-2013 capacity] at that date).

(8) This article is subject to article 32.

Textual Amendments