Search Legislation

The Renewables Obligation (Scotland) Order 2009

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Section 36

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the The Renewables Obligation (Scotland) Order 2009, Section 36. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

General criteria for the issue of SROCs

This section has no associated Executive Note

36.—(1) Subject to article 37, once during each obligation period the person to whom a SROC is to be issued must confirm to the Authority in writing, whether before or after the generation of the electricity to which the SROC relates, that that electricity, to the best of the person's knowledge and belief, has been or (as the case may be) will be–

(a)in the case of a SROC certifying the matters within section 32B(3) or (5) of the Act, supplied by a designated electricity supplier to customers in Great Britain;

(b)in the case of a SROC certifying the matters within section 32B(4) or (6) of the Act, supplied by a Northern Ireland supplier to customers in Northern Ireland; and

(c)in the case of a SROC certifying the matters within section 32B(7) or (8) of the Act, used in a permitted way.

(2) The electricity in respect of which a SROC is to be issued–

(a)must be generated during a month in which the generating station generating it is accredited under this Order or an Order made under Article 52 of the Northern Ireland Energy Order and any conditions to which the accreditation is subject are met;

(b)subject to paragraph (3), must be measured using a meter which, if used for ascertaining the quantity of electricity supplied by an authorised supplier to a customer, would be approved for the purposes of paragraph 2(1)(a) of Schedule 7 to the Act; and

(c)must not include electricity in respect of which a SROC–

(i)has already been issued under this Order and has not been revoked; or

(ii)has already been issued under an Order made under sections 32 to 32M of the Act by the Secretary of State (whether or not it has been revoked).

(3) Paragraph (2)(b) does not apply in relation to electricity generated by a generating station the operator of which has agreed with the Authority that estimates may be provided instead of measurements using a meter.

(4) Any information which–

(a)is relevant to the question whether a SROC is to be issued; and

(b)is requested by or required to be provided to the Authority under article 53 (provision of information to the Authority),

must be provided in the form and time requested and must be (in the Authority's opinion) accurate and reliable.

(5) Where such information relates to the fuel used in the generation of that electricity and the fuel did not originate at the generating station, in determining whether that information is accurate and reliable the Authority must have regard to–

(a)the distance over which the fuel was transported; and

(b)the conditions under which the fuel was prepared and transported.

[F1(6) The operator of a generating station which generates electricity by burning fuel in a combustion unit may notify the Authority in writing that, until such time as the notification is withdrawn, the energy content of any biomass burned in that combustion unit will be less than 50 per cent of the energy content of all the energy sources burned in that combustion unit.

(7) A notification under paragraph (6) constitutes sufficient evidence of the fact that the energy content of the biomass burned in the combustion unit referred to in the notification is less than 50 per cent of the energy content of all the energy sources burned in that combustion unit.

(8) A notification under paragraph (6) may be withdrawn by a notice—

(a)in writing from the operator of the generating station to the Authority; and

(b)which specifies a date from which the withdrawal of the notification is to take effect.]

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Executive Note

Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources