Changes over time for: Paragraph 11
Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 30/03/2016
Status:
Point in time view as at 01/12/2013.
Changes to legislation:
The Waste Management Licensing (Scotland) Regulations 2011, Paragraph 11 is up to date with all changes known to be in force on or before 07 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
This section has no associated Executive Note
11.—(1) Carrying on at any place, in respect of waste of a kind listed in column 1 of Table 5, any of the activities specified in column 2 of that Table in relation to that kind of waste where—S
(a)the activity is carried on with a view to the recovery or reuse of the waste (whether or not by the person carrying on the activity listed in column 2 of that Table); and
(b)the total quantity of any particular kind of waste dealt with at that place does not in any period of 7 days exceed the limit specified in relation to that kind of waste in column 3 of that Table.
Table 5
1 includes special waste.
|
Kind of waste | Activities | Maximum total quantity (tonnes per week) |
---|
Waste paper or cardboard | Baling, sorting or shredding | 3,000 |
|
Waste textiles | Baling, sorting or shredding | 100 |
|
Waste plastic | Baling, sorting, shredding, densifying, pelletising or washing | 100 |
|
Waste glass | Sorting, crushing or washing | 1,000 |
|
Waste steel cans, aluminium cans or aluminium foil | Sorting, crushing, pulverising, shredding, compacting or baling | 100 |
|
Waste food or drink cartons | Sorting, crushing, pulverising, shredding, compacting or baling | 100 |
|
Waste tyres | Baling, sorting or shredding | 10 |
|
Waste wood | Baling, compacting, sorting or shredding | 1,000 |
|
Waste paint | Sorting, bulking or mixing | 100 |
|
Waste batteries1 | Sorting | 10 |
(2) The storage of waste paints intended to be used in reliance on the exemption in sub-paragraph (1).
(3) In the case of any waste batteries, sorting must take place in accordance with the treatment conditions.