SCHEDULE 10SAVINGS AND TRANSITIONAL PROVISIONS
F1Part 5Medium Combustion Plant
15
1
Regulation 11 applies to a new medium combustion plant with a rated thermal input equal to or greater than 1 megawatt and less than or equal to 20 megawatts on and after 20th December 2018.
2
Regulation 11 applies to existing medium combustion plant on and after—
a
1st January 2024, where the rated thermal input of the plant is greater than 5 megawatts,
b
1st January 2029, where the rated thermal input of the plant is less than or equal to 5 megawatts.
3
Paragraph 1(1) of schedule 1B applies to an existing medium combustion plant from 1st January 2025.
4
Paragraph 1(2) of schedule 1B applies to an existing medium combustion plant from 1st January 2030.
5
An application for a permit to operate an existing medium combustion plant must be received by SEPA by—
a
30th June 2023, where the rated thermal input of the plant is greater than 5 megawatts and less than or equal to 20 megawatts,
b
30th June 2028, where the rated thermal input of the plant is less than or equal to 5 megawatts.
6
Paragraph 1(1) and (2) of schedule 1B applies to an existing medium combustion plant which is part of a small isolated system or a micro isolated system on and after 1st January 2030.
7
In this paragraph “small isolated system” and “micro isolated system” have the same meaning as in paragraph 10 of schedule 1B.
Sch. 10 Pt. 5 inserted (19.12.2017) by The Pollution Prevention and Control (Scotland) Amendment Regulations 2017 (S.S.I. 2017/446), regs. 1(1), 16