Search Legislation

The Pollution Prevention and Control (Scotland) Regulations 2012

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: SCHEDULE 1A

 Help about opening options

Alternative versions:

Status:

Point in time view as at 31/12/2020.

Changes to legislation:

The Pollution Prevention and Control (Scotland) Regulations 2012, SCHEDULE 1A is up to date with all changes known to be in force on or before 10 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

Regulation 20A

[F1SCHEDULE 1ASEnergy Efficiency Directive

This schedule has no associated Policy Notes

Application of ScheduleS

1.  Subject to paragraphs 2 and 3, this Schedule applies to—

(a)a thermal electricity generation installation with a total thermal input exceeding 20 megawatts,

(b)an industrial installation with a total thermal input exceeding 20 megawatts generating waste heat at a useful temperature level, or

(c)an energy production installation with a total thermal input exceeding 20 megawatts in an existing district heating or cooling network,

for which an application for a permit, or an application for a variation of a permit due to a substantial refurbishment, is made on or after 30th October 2014.

2.(1) This Schedule does not apply to individual installations, except an installation which forms part of a district heating and cooling network, with any of the following—

(a)available waste heat of 100 kilowatts or less,

(b)available waste heat—

(i)greater than 100 kilowatts as hot water or steam, where there is no hot water heat demand greater than 100 kilowatts within the search radius from the source installation as set out in the table, located within the connection distance from the centre of the source installation, or

(ii)greater than 500 kilowatts as steam where there is no steam-based heat demand greater than 500 kilowatts within the search radius from the centre of the installation as set out in the table, located within the connection distance from the centre of the source installation,

(c)a heat demand of—

(i)100 kilowatts or less for a hot water heat demand, or

(ii)500 kilowatts or less for a steam-based heat demand,

(d)a hot water heat demand greater than 100 kilowatts, with no source of available waste heat greater than 100 kilowatts within the search radius from the centre of the demand installation as set out in the table, located within the connection distance from the centre of the demand installation, or

(e)a steam-based heat demand greater than 500 kilowatts, with no source of steam-based waste heat greater than 500 kilowatts within the search radius from the centre of the installation as set out in the table, located within the connection distance from the centre of the demand installation.

(2) For the purposes of this paragraph, “connection distance” means—

(a)in the case of a hot water link, the thermal capacity in kilowatts of the source or demand, whichever is smaller, multiplied by 0.0038, or

(b)in the case of a steam heat link, the thermal capacity in kilowatts of the source or demand, whichever is smaller, multiplied by 0.0012,

expressed in kilometres.

TABLE

Search radius

Installation typeThermal capacity of heat source/demandSearch radius (kilometres), measured from the centre of the installation
Hot water demand>100 kilowatts and <3.9 megawatts0.0038 x H, where H = thermal capacity in kilowatts
3.9 megawatts15
Steam demand>500 kilowatts and <12.5 megawatts0.0012 x H, where H = thermal capacity in kilowatts
12.5 megawatts15
Waste heat source (hot water or steam)>100 kilowatts and <3.9 megawatts0.0038 x H, where H = thermal capacity in kilowatts
3.9 megawatts15

3.  This Schedule does not apply to—

(a)peak load and back-up electricity generating installations which operate or are planned to operate under 1,500 operating hours per year as a rolling average over a period of five years,

(b)nuclear power installations, or

(c)installations that need to be located close to a geological storage site [F2for which a licence has been granted under section 18 of the Energy Act 2008].

[F33A.(1) Where this schedule does not apply to an installation by virtue of paragraph 3(a), SEPA must take appropriate steps to verify that the exemption criteria are met.S

(2) SEPA may comply with sub-paragraph (1) by—

(a)service of notice under regulation 63(2) requiring the operator of the installation to provide information required to verify the installation’s operating hours,

(b)inclusion of appropriate conditions in a permit for an installation of which the installation falling within paragraph 3(a) forms part.]

Applications and cost-benefit analysisS

4.  Subject to paragraph 5, an application for a permit under regulation 13 for an installation to which this Schedule applies must provide a cost-benefit analysis.

5.  An application in respect of a Part B installation where no activity listed in Schedule 1 other than the activity described in paragraph (c) of Part B of Section 1.1 of Schedule 1 will be carried out need include only—

(a)the information described in paragraph 1(1)(a) to (c), (f) and (s) of Schedule 4, and

(b)a cost-benefit analysis.

6.  Paragraphs 4 and 5 do not apply to any installation for which an application for a permit was made before 30th October 2014.

7.  No person may carry out a substantial refurbishment of an installation to which this Schedule applies except under and to the extent authorised by a permit.

8.  Where there is a proposed change in operation at an installation to which this Schedule applies, the operator of which has been granted a permit, and the change—

(a)results in an application for variation under regulation 46, and

(b)constitutes a substantial refurbishment,

the operator must include a cost-benefit analysis in addition to the information required by paragraph 1 of Schedule 7.

9.  Where there is a proposed change in operation at an installation to which this Schedule applies, the operator of which has been granted a permit, and the change—

(a)does not result in an application for variation under regulation 46, and

(b)constitutes a substantial refurbishment,

the operator must submit to SEPA the information described in paragraph 1(a) to (c) of Schedule 7, and a cost-benefit analysis.

10.  The requirements of paragraphs 8 and 13 of Schedule 4 and paragraph 4(4)(c) and (8) of Schedule 7 do not apply to an application in respect of a Part B installation where no activity listed in Schedule 1 other than the activity described in paragraph (c) of Part B of Section 1.1 is or will be carried out.

11.  The cost-benefit analysis must be carried out in accordance with Part 2 of Annex IX of the Energy Efficiency Directive and must—

(a)in the case of a thermal electricity generation installation, assess the costs and benefits of operating the installation or converting the installation to operate as a high-efficiency cogeneration installation,

(b)in the case of an installation which forms part of an existing or planned district heating and cooling network, assess the costs and benefits of utilising the waste heat from nearby industrial installations, or

(c)in the case of any other industrial installation generating waste heat at a useful temperature, assess the costs and benefits of utilising the waste heat to satisfy economically justifiable demand, including through cogeneration, and of the connection of that installation to a district heating and cooling network.

Determination of applicationsS

12.  When considering an application for a permit, or for a variation of permit, in respect of an installation to which this Schedule applies, SEPA must take into account—

(a)the outcome of the cost-benefit analysis required by paragraph 4, 8 or 9, and

(b)from 31st December 2015, the outcome of any comprehensive national assessment [F4carried out in compliance with] Article 14(1) of the Energy Efficiency Directive.

13.  Where a cost-benefit analysis required in the case referred to in paragraph 11(a) or (c) shows that benefits exceed costs, SEPA must ensure that the permit includes conditions that will ensure the operation of the installation in a manner shown by that analysis to be cost beneficial.

14.  Where a cost-benefit analysis required in the case referred to in paragraph 11(b) shows that benefits exceed costs, SEPA must ensure that the permit includes conditions that will ensure the operation of the installation, in conjunction with the utilisation of the waste heat from nearby industrial installations, in a manner shown by that analysis to be cost beneficial.

15.  SEPA must ensure, in respect of a permit for a Part B installation at which the only activity listed under the heading “Part B” in Section 1.1 of Part 1 of Schedule 1 carried out is that described in paragraph (c) of Part B of that Section, that the permit includes only such conditions as SEPA considers necessary to comply with [F5this schedule], and any requirement in these Regulations to include any other condition does not apply in respect of the permit to that extent.

16.  Paragraphs 13 and 14 do not apply if SEPA decides that there are imperative reasons of law, ownership or finance for them not to apply in respect of any permit application or variation.

17.  SEPA must, in any case where it makes a decision in accordance with paragraph 16, submit a reasoned notification of it to the Scottish Ministers within two months after the date of the decision.

InterpretationS

18.[F6(1)] In this Schedule—

“cogeneration” means the simultaneous generation in one process of thermal energy and electrical or mechanical energy,

“cost-benefit analysis” means a cost-benefit analysis carried out in accordance with Part 2 of Annex IX of the Energy Efficiency Directive,

“economically justifiable demand” means demand that does not exceed the needs for heating or cooling and which would otherwise be satisfied at market conditions by energy generation processes other than cogeneration,

“high-efficiency cogeneration” means cogeneration meeting the criteria laid down in Annex II of the Energy Efficiency Directive,

“substantial refurbishment” means a refurbishment whose cost exceeds 50% of the investment cost for a new comparable unit; but the fitting of equipment to carry out the activity described in Part A of Section 6.10 of Part 1 of Schedule 1 shall not be considered as a substantial refurbishment, and

“unit” means any boilers, furnaces, turbines or compression ignition engines forming part of an installation which added together have a rated thermal input of more than 20 megawatts.

[F7(2) For the purposes of sub-paragraph (1), Annex II of the Energy Efficiency Directive is to be read as if —

(a)in the seventh subparagraph of point (b) (beginning “CHP Eη”), the last sentence were omitted,

(b)in point (c), for “Member States may” there were substituted “ It is permissible to ”,

(c)in point (d)—

(i)the words “Member States may use” were omitted,

(ii)after “one year” there were inserted the words “ may be used ”.

(3) For the purposes of paragraphs 11 and 18(1), Part 2 of Annex IX of the Energy Efficiency Directive is to be read as if—

(a)in the heading, for “Article 14(5) and (7)” there were substituted “ paragraphs 11, 13 and 14 ”,

(b)in the first paragraph, for “the measures in Article 14(5) and (7)” there were substituted “ paragraphs 11, 13 and 14 of schedule 1A of the Pollution Prevention and Control (Scotland) Regulations 2012 ”,

(c)in the eighth paragraph, the words “for the purposes of Article 14(5)” were omitted,

(d)in the tenth and eleventh paragraphs, for “Member States”, at each place it occurs, there were substituted “ the Scottish Ministers ”.]]

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Policy Note

Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources