SCHEDULE 6SCOMPENSATION FOR OFF-SITE CONDITIONS

5.—(1) An application for compensation under this Schedule must be made by the person granting an off-site right—S

(a)within six months from the date on which the right is first exercised, or

(b)within 12 months from the date on which the entitlement to compensation arises in the case of that grantor.

(2) An application must be made in writing to an operator to whom the off-site right is granted at the last known address for correspondence of the operator.

(3) The application must contain, or be accompanied by—

(a)a copy of the grant of an off-site right in respect of which the compensation is payable, and of any plans attached to that grant,

(b)a description of the exact nature of any interest in land in respect of which compensation is applied for,

(c)a statement of the amount of compensation applied for, distinguishing the amounts applied for under each sub-paragraph of paragraph 3, and showing how the amount applied for under each sub-paragraph has been calculated, and

(d)where the date on which the entitlement to compensation arises is ascertained in accordance with paragraph 4(2), a copy of the notice of the final determination of the appeal.