Print Options
PrintThe Whole
Instrument
PrintThe Whole
Part
PrintThe Whole
Chapter
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Section 42
Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 18/04/2016.
Changes to legislation:
The Public Contracts (Scotland) Regulations 2015, Section 42 is up to date with all changes known to be in force on or before 10 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Prior involvement of candidates or tenderersS
This section has no associated Policy Notes
42.—(1) A contracting authority must take appropriate measures to ensure that competition is not distorted by the participation of a candidate or tenderer where that candidate or tenderer, or an undertaking related to that candidate or tenderer—
(a)has advised the contracting authority, whether in the context of regulation 41 (preliminary market consultation) or not; or
(b)has otherwise been involved in the preparation of the procurement.
(2) Such measures must include—
(a)the communication to the other candidates and tenderers of relevant information exchanged in the context of or resulting from the involvement of the candidate or tenderer in the preparation of the procurement procedure; and
(b)the fixing of adequate time limits for the receipt of tenders.
(3) A candidate or tenderer in a situation referred to in paragraph (1) may only be excluded from the procedure for the purpose of paragraph (1) where there are no other means to ensure compliance with the duty referred to in regulation 19(1) (principles of procurement).
(4) Prior to any such exclusion, a candidate or tenderer must be given the opportunity to prove that their involvement in preparing the procurement procedure is not capable of distorting competition.
(5) The measures taken must be documented in the report referred to in regulation 83(1) (reporting and documentation requirements).