PART 2RULES IMPLEMENTING THE PUBLIC CONTRACTS DIRECTIVE

CHAPTER 2RULES ON PUBLIC CONTRACTS

SECTION 6Contract Performance

Termination of contracts73

1

A contracting authority must ensure that every public contract or framework which the authority awards contains provisions enabling the authority to terminate the contract or framework where—

a

the contract or framework has been subject to a substantial modification which would have required a new procurement procedure in accordance with regulation 72(9) (modification of contracts during their term);

b

the contractor has, at the time of contract award, been in one of the situations referred to in regulation 58(1) (exclusion grounds), including as a result of the application of regulation 58(2), and should therefore have been excluded from the procurement procedure; or

c

the contract or framework should not have been awarded to the contractor in view of a serious infringement of the obligations under the Treaties and the Directive that has been declared by the Court of Justice of the European Union in a procedure under Article 258 of the TFEU.

2

Those provisions may address the basis on which the power is to be exercisable in those circumstances, for example by providing for notice of termination to be given and by addressing consequential matters that will or might arise from the termination.

3

To the extent that a public contract or framework does not contain provisions enabling the contracting authority to terminate the contract or framework on any of the grounds mentioned in paragraph (1), a power for the contracting authority to do so on giving notice to the contractor shall be an implied term of that contract or framework.