1. Introductory Text

  2. PART 1 Preliminary

    1. 1.Citation and commencement

    2. 2.Application of Regulations

    3. 3.Interpretation

    4. 4.Meaning of prospective buyer or prospective tenant

  3. PART 2 Assessment of Energy Performance

    1. 5.Action plans on sale or rent of non-domestic buildings

    2. 6.Action Plans

    3. 7.Energy performance target and emissions target

  4. PART 3 Implementation of action plans or operational rating measures

    1. 8.Implementation of building improvement measures

    2. 9.Confirmation of completion of building improvement measures

    3. 10.Implementation of operational rating measures

    4. 11.Display Energy Certificate

    5. 12.Advisory report

  5. PART 4 Approved organisations

    1. 13.Approved organisations

  6. PART 5 Register of energy improvement data

    1. 14.Registration of energy improvement data

    2. 15.Disclosures generally

    3. 16.Disclosure of documents

    4. 17.Disclosure of data relating to a particular building or building unit

    5. 18.Disclosure of bulk access data

    6. 19.Disclosure of data

  7. PART 6 Enforcement

    1. 20.Enforcement authorities

    2. 21.Power to require production of action plan

    3. 22.Penalty charge notices – failure to provide action plan

    4. 23.Defence where action plan unobtainable

    5. 24.Penalty charge notice - failure to implement building improvement measures

    6. 25.Reviews

    7. 26.Appeal to the sheriff court

    8. 27.Recovery of penalty charges

    9. 28.Repayment of penalty charge

  8. Signature

    1. SCHEDULE

      Identified Improvement Measures

      1. 1.The identified improvement measures in respect of a building or...

      2. 2.The improvement measures are— (a) installing draught stripping to doors...

      3. 3.The criteria are— (a) in the case of improvement measures...

  9. Explanatory Note